Annual Report to shareholders
Released
Released
Announcement PDF
Annual Report 2026
Andromeda Metals Limited
2
Company information
Directors
Sue-Ann Higgins Executive Chair
Mick Wilkes Independent
Non-executive Director
Jean-Dominique Sorel Non-executive Director
Miguel Galindo Non-executive Director
Company Secretary
Sarah Clarke Acting CEO,
General Counsel and
Company Secretary
Andromeda Metals Limited
ABN: 75 061 503 375
ASX code: ADN
Registered and Principal Address
Level 10, 431 King William Street
Adelaide, South Australia 5000
Contact Details
Telephone: +61 8 7089 9800
ir@andromet.com.au
www.andromet.com.au
Share Registry
Computershare Investor Services Pty Ltd
Yarra Falls, 452 Johnston Street
Abbotsford, VIC 3067
GPO Box 2975, Melbourne VIC 3001
Enquiries (within Australia): 1300 556 161
Enquiries (outside Australia): +61 3 9415 4000
Auditors
Deloitte Touche Tohmatsu
11 Waymouth Street
Adelaide, South Australia 5000
Solicitors
Minter Ellison Lawyers
25 Grenfell Street
Adelaide, South Australia 5000
Bankers
Westpac Banking Corporation
Level 5, 97 King William Street
Adelaide, South Australia 5000
Annual Report 2026 3
Contents
Letter from the Chair 4
Acting CEO’s report 6
Operations review 10
The Great White Project 12
HPA Project 21
Exploration 24
Great White Deposit 25
Hammerhead Deposit 26
Tiger Deposit 27
Eyre Kaolin Project 28
Mount Hope Kaolin Project 29
Corporate 31
Sustainability 33
Resources and reserves 43
Competent person statements 48
Schedule of tenements 49
Directors’ report 50
Directors and key management personnel 51
Operating and Financial Review 57
Remuneration report (audited) 61
Auditors Independence Declaration 88
Financial report 89
Directors’ Declaration 127
Independent Auditor’s Report
128
Shareholder information 133
Glossary 138
Andromeda Metals Limited
4
Letter from the Chair
Dear Shareholders,
Andromeda continues its focus on delivering the
next generation of superior-quality industrial and
critical minerals.
The 2026 financial year was defined by disciplined
execution, careful capital management and
continued progress towards unlocking the value of
Andromeda’s Great White Project (GWP) and our
promising High Purity Alumina (HPA) opportunity.
Against a challenging macroeconomic and
funding environment, the Company completed
important pre-construction Early Works activities
at the Great White Project, advanced funding
pathways, built and commissioned a HPA pilot
plant and continued to protect shareholder value
through managing our costs and implementing
targeted cost reduction strategies.
The Great White Project remains the cornerstone
of Andromeda’s strategy. During the year, the
Company completed pre-construction Early
Works, including establishment of mine access,
bulk earthworks for the Stage 1A+ processing plant,
geotechnical and grade control drilling, and the
transport of key long lead equipment to Australia.
This now sees the GWP as being significantly de-
risked and development-ready.
Having previously received credit-approval from
Merricks Capital for a $75 million debt facility, the
Company continued to pursue the balance of
funding required to support an anticipated FID.
Following the completion of Early Works at the GWP,
the estimated balance of equity funding required
was reduced to approximately $40 million1
.
To support this, engagement with a Middle East-
based cornerstone investor progressed through
due diligence with negotiations on key commercial
terms and documentation having reached the
final stages, although completion was delayed by
the geopolitical developments surrounding the
war with Iran. While remaining engaged with the
cornerstone investor, the Company is assessing
a range of funding, strategic and corporate
opportunities to unlock value from the GWP.
Discussions with potential investors are typically
commercial-in-confidence and subject to
confidentiality obligations, particularly while
negotiations are ongoing. For this reason, it
would not be appropriate, or in shareholders’
best interests, to disclose the terms, structure or
status of those negotiations prior to execution of
binding agreements. Premature disclosure could
prejudice negotiations, limit strategic flexibility
and risk misinforming the market. Rest assured
shareholders will be updated when it is appropriate
to do so.
In parallel with the funding process for the GWP,
after considering relevant information, risks and
opportunities, the Board formed the view that
continuing to advance our critical mineral HPA
Project was in the best interests of the Company
and its shareholders.
The financial year saw the HPA Project advance
materially, with a number of milestones achieved.
1
This estimate is indicative only and subject to change due to
economic conditions, funding structure assumptions and the proposed
arrangements with Merricks Capital. The estimate does not factor in the
potential impacts of recent geopolitical events, including possible effects
on diesel pricing or availability.
Annual Report 2026 5
The 2025 Scoping Study was completed, showing
strong results and market-leading economics of
producing the HPA and supports the Company’s
strategy to create additional value from Great
White kaolin and our proprietary processing
technology. Following commissioning of the
pilot plant, an optimisation and continuous
testwork program to support market engagement
activities remains underway. This supports a pilot
testwork program which is designed to produce
commercial 4N HPA samples for prospective
customers and assess the potential value of co-
products, including amorphous silica and gallium.
In August 2026, two significant milestones for the
HPA Project were achieved:
• successful production of HPA with a measured
purity of 99.9986%, significantly exceeding the
4N specification threshold of 99.99%, through
the continuous pilot plant using Great White
kaolin as feedstock;2
and,
• building on our existing collaboration with
Traxys, the company signed a non-binding
Heads of Agreement (HOA) with Traxys North
America, LLC to advance a strategic pathway
for the supply of HPA into the United States3
.
Capital management remained a priority. The
Company raised more than $14 million before
costs through the October 2025 Placement and
associated Share Purchase Plan (SPP) offer to
shareholders which closed in November 2025.
These funds supported the Early Works activities
at the GWP, the procurement, transport and
storage of long lead equipment items, payment
of rehabilitation bond, progressing the HPA Project,
and product marketing activities in support of both
the GWP and HPA Project.
Following the end of FY26, shareholders were
again invited to apply for another SPP which
closed in August 2026. I am pleased to report that
shareholders supported the SPP and an associated
placement on the same terms, which raised a total
of $3.04 million to support the advancement of
the HPA Project, including supporting completion
of a pre-feasibility study (PFS), for general working
capital and costs of the capital raise.
Tightly managing costs was also a feature with
cost-saving and cash conservation measures
implemented during the financial year. This
included continuation of voluntary reductions in
director fees, minimising discretionary expenditure,
salary savings from non-replacement of personnel
and some staff reducing their hours to being
part-time, and the granting of zero exercise price
options (ZEPOs) in lieu of part payment of director
fees. In total, these measures conserved over
$3 million in cash payments during the financial
year, reflecting our shared commitment to the
Company’s success and our belief in the value we
are creating.
The Board remains committed to responsible
financial and business practices, and the highest
standards of corporate governance. I invite you to
read about these in the Director’s Report starting
on page 50 of this Report.
I take this opportunity to thank you, our
shareholders, for your continued support, and our
employees for their dedication during the year. In
particular, the Board thanks Sarah for her strong
leadership in guiding the team as Acting CEO in
addition to her existing management duties as
General Counsel and Company Secretary.
Similarly, our successes could not have been
achieved without the support of our offtake
partners, suppliers and the local Eyre Peninsula
community.
In FY27, the Board’s priority is clear: secure a value-
accretive funding pathway for the Great White
Project and advance HPA commercialisation
activities so as to maximise long-term value for
you, our shareholders.
Yours sincerely,
Sue-Ann Higgins
Executive Chair
2
Refer ADN ASX dated 24 August 2026 titled Andromeda Achieves 4N
(99.9986%) HPA at Continuous Pilot Scale, Advancing Commercialisation.
3
Refer ADN ASX dated 19 August 2026 titled Andromeda Signs Strategic
HPA Supply HOA with Traxys Supporting US Critical Minerals Supply Chain
Initiative.
Andromeda Metals Limited
6
Acting CEO’s report
Dear Shareholders,
During FY26, Andromeda progressed two
complementary value drivers for our business: the
development-ready Great White Project, and the
commercialisation pathway for our proprietary HPA
process. The GWP continues to be the cornerstone
of our strategy for positioning the Company for
long-term success in the industrial minerals sector.
Our HPA Project represents an opportunity for
Andromeda to enter into critical minerals markets
by leveraging our high-quality Great White kaolin
as feedstock and using our proprietary processing
technology to produce High Purity Alumina (HPA).
Great White Project progressed
Following satisfaction of $4.5 million in environment
compliance obligations4
, pre-construction Early
Works were completed during FY26. This included
construction of mine site access, bulk earthworks
for the processing plant pad area, geotechnical
and grade control drilling. In addition, key long-
lead equipment items fabricated and warehoused
overseas, were successfully transported to
Australia for storage.
Together, these represent tangible progress which
now sees Andromeda in an advanced stage of
preparedness, being construction-ready with a
committed Project Team in place and poised for
delivery.
During FY26, the Company continued to pursue
the balance of funding required for Stage 1A+. Due
diligence with a cornerstone investor based in the
Middle East was completed and negotiations had
reached an advanced stage before geopolitical
developments interrupted the process. While
remaining engaged with the cornerstone investor,
the Company assessed other funding, strategic
and corporate alternatives to unlock value from
the GWP and pursue its business objectives.
Following completion of Early Works activities
and through maintaining capital discipline, the
estimated balance of equity funding required to
support a final investment decision was reduced to
approximately $40 million5
, alongside the credit-
approved $75 million debt facility with Merricks
Capital6
.
Future growth opportunities
While progressing project funding discussions,
the Company continues to pursue future growth
opportunities. Stage 1A+ is the initial stage of
GWP, with other product and customer growth
opportunities being pursued to support future
expansions over GWP’s three development stages.
4
Includes lodgement of a $3.79 million rehabilitation bond and payment
of $670,000 to the Native Vegetation Fund to satisfy the Significant
Environmental Benefit (SEB) obligations.
5
This estimate is indicative only and subject to change due to
economic conditions, funding structure assumptions and the proposed
arrangements with Merricks Capital. The estimate does not factor in the
potential impacts of recent geopolitical events, including possible effects
on diesel pricing or availability.
6
Final approvals and execution of a binding agreement remain subject to
finalisation of balance of funding for Stage 1A+.
Annual Report 2026 7
HPA Project
FY26 marked another important year in the
pathway of commercialisation of Andromeda’s
High Purity Alumina Project, meaningfully
progressing Andromeda’s ambitions to enter the
market for critical minerals.
The completion of a Scoping Study during the
financial year demonstrated market-leading
economics and the opportunity for Andromeda to
become a leading global supplier of low-cost,
low-carbon HPA. Key findings of the HPA Scoping
Study were:
• Potential Net Present Value (NPV10
) of ~$1,010
million post tax and post-tax internal rate of
return (IRR) of 69%
• Capital expenditure of $155 million giving
market-leading capital intensity of $15,459 per
tonne of HPA capacity (US$9,894/t)
• Operating costs of approximately $4,718 per
tonne significantly below other globally reported
processes
• Low-carbon HPA processing technology – with
modelled carbon emissions up to 48% lower
than traditional aluminium alkoxide process;
and
• Andromeda’s technology using a kaolin
feedstock has the potential to disrupt the
existing HPA market
This underpinned the decision to advance to the
next stage of commercialisation by commencing
a pilot-scale testwork program, to further validate
and optimise our proprietary HPA flowsheet and
produce commercial samples.
Consequently, the required metallurgical
components for a pilot plant were designed
and manufactured, before being assembled in
Australia. Commissioning of the HPA pilot plant
was completed shortly after the conclusion of
FY26, which enabled an optimisation and testwork
program to commence, which remains ongoing.
The program aims to produce commercial
samples for prospective customers to evaluate,
in addition to allowing the assessment of whether
certain by-product materials, including amorphous
silica and gallium, can be re-classed as co-
products and add further value to the project.
In August 2026, a significant milestone was
achieved, following the successful production
of HPA with a measured purity of 99.9986%,
significantly exceeding the 4N specification
threshold of 99.99%, through the continuous pilot
plant using Great White kaolin as feedstock7
.
Also in August 2026, building on its existing
collaboration with Traxys, the Company signed
a non-binding Heads of Agreement (HOA) with
Traxys North America, LLC to advance a strategic
pathway for the supply of HPA into the United
States8
. The HOA establishes the framework for
negotiating a potential five-year sales agency
agreement, targeting an indicative sales volume
of 2,000 tonnes of HPA per annum to the United
States. Based on indicative pricing of US$20,000 per
tonne, this equates to a potential annual sales of
approximately US$40 million9
, with final pricing to
be determined based on market conditions at the
time of industrial production.
7
Refer ADN ASX dated 24 August 2026 titled Andromeda Achieves 4N
(99.9986%) HPA at Continuous Pilot Scale, Advancing Commercialisation.
8
Refer ADN ASX dated 19 August 2025 titled Andromeda Signs Strategic
HPA Supply HOA with Traxys Supporting US Critical Minerals Supply Chain
Initiative.
9
This assumes the average market pricing adopted in the Company’s 2025
Scoping Study, which was based on market analysis at the time (refer
ASX ADN dated 18 June 2025 titled Results of HPA Scoping Study), without
taking into account any fees or costs associated with the sale.
Andromeda Metals Limited
8
Disciplined financial and capital management
Andromeda’s strategic focus remains on
developing the GWP and progressing the
commercialisation of the HPA opportunity. To
support the Company while the funding process
to secure is underway, a number of initiatives were
implemented to raise capital, reduce costs and
conserve cash.
A capital raising raised over $14 million before
costs, via:
• Share Placement – a placement of new fully
paid ordinary shares which raised $13 million,
with significant demand from institutional and
sophisticated investors;
• Share Purchase Plan (SPP) – to eligible
shareholders on the same terms as the Share
Placement, which raised $996,000; and
• $30,000 participation by a Director who was not
a shareholder at the time of the Capital Raising,
with the securities issued following shareholder
approval obtained at a General Meeting held on
10 December 2025.
Listed options were issued as part of these offers.
The value of these, together with pre-existing
options, if exercised will provide the company with
an additional $24.4 million in working capital.
This was followed with shareholders supporting
the company in August 2026, through an SPP and
an associated placement on the same terms,
which raised a total of $3.04 million to support
the advancement of the HPA Project, including
supporting completion of a pre-feasibility study
(PFS).
During FY26, the Company continued to prudently
manage costs during the period, including through
implementing approximately $3 million in cost
savings and deferred spending across Early
Works, procurement, remuneration expenses and
administrative costs.
People, safety and environment
Our team completed a significant work program
while maintaining an emphasis on safety,
environmental compliance and community
stakeholder engagement.
Looking ahead
Progressing GWP continues to represent the best
opportunity to maximise long-term value for
Andromeda and its shareholders and we remain
confident of its fundamentals and excited about
the opportunities ahead.
As we move towards a final investment decision,
our focus remains on securing funding and
preparing for construction for the GWP, as well as
unlocking further value by progressing the HPA
Project.
In closing, I would like to thank our team, Board,
shareholders, and partners for their unwavering
support.
Together, we are looking to build a resilient,
innovative, and future-focused industrial and
critical minerals company, to deliver long-term
value for you, our shareholders, the local Eyre
Peninsula community and South Australia.
Yours sincerely,
Sarah Clarke
Acting CEO, General Counsel and
Company Secretary
Annual Report 2026 9
Andromeda Metals Limited
10
Operations review
Andromeda Metals is an Australian company focused on
delivering the next generation of superior-quality industrial
and critical minerals.
Corporate strategy
Advance development of its portfolio of
high-quality kaolin resources and processing
technologies to supply the next generation of
superior-quality industrial and critical minerals into
established and emerging global markets.
Leverage our high-quality kaolin resources with a
product portfolio tailored to high-value ceramics,
porcelain and low-carbon concrete markets
and further develop proprietary processing
technologies to enter critical minerals markets.
FY26 strategic focus
Advance the Great White Project towards a final
investment decision, position the Company for
efficient construction and delivery of the initial
Stage 1A+, and progress commercialisation of
the high purity alumina (HPA) opportunity.
Annual Report 2026 11
10
Refer to Table of Reserves – Great White Deposit on page 46. The 15.1 Mt Ore Reserves includes 5.2 Mt classed as Proved and 10.0 Mt as Probable.
11
Refer to 2023 DFS section on page 20, upon which the forecast financial information relates to an Ore Reserve Estimate that has been previously announced
to ASX on 6 April 2022 titled Great White Kaolin Project – Definitive Feasibility Study and Updated Ore Reserve. Andromeda confirms that it is not aware of any
new information or data that materially affects the information included in these market announcements (unless otherwise stated) and that all material
assumptions and technical parameters underpinning the estimates and forecast financial information continue to apply and have not materially changed.
Industrial Minerals Critical Minerals
GREAT WHITE
PROJECT (GWP)
EYRE KAOLIN
PROJECT
MOUNT HOPE
KAOLIN PROJECT
HPA
PROJECT
PROJECT
OVERVIEW
Development-ready
flagship kaolin project
supported by 15.1 Mt
Ore Reserve10
2023 DFS shows
strong economics
through a 3 staged
development over a
28-year life-of-mine11
51% interest in the Eyre
Kaolin Joint Venture,
with four exploration
licences covering
2,799 km2
Exploration being
undertaken for kaolin
with properties
complementary to
those of the Great
White Deposit.
100% interest in
tenements, over which
significant areas
of ultra-high bright
white kaolin, with
exceptionally low iron
contaminant levels,
have been defined.
Proprietary process
developed over 8 years
of R&D to produce high
purity alumina from
kaolin
Proprietary process
proven at lab-scale
to produce HPA to
99.9985% purity
Opportunity to become
a market-leading global
supplier of low-cost,
low-carbon HPA
FY26
OUTCOMES
On site Early Works
completed
Transportation of key
long lead equipment
items and storage in
Australia completed
Progressed project
funding process to
secure balance of
funding to support FID
Postponed in-house
analysis of the 2025
Chairlift drill samples
to prioritise Great
White grade control
drilling
Tenement maintained
Continued
consideration of
exploration and
evaluation activities.
HPA Pilot Plant
commissioned
Commencement of
pilot plant optimisation
and testwork program
Continuous pilot scale
4N+ HPA produced to
99.9986%
Strategic HPA Heads of
Agreement signed with
Traxys for US Market
Andromeda Metals Limited
12
The Great White Project
SOUTH AUSTRALIA
100% Andromeda
The Great White Project is located on South
Australia’s Eyre Peninsula, approximately 635 km
west by road from Adelaide and approximately 15
kilometres south-west of Poochera (see Figure 1).
It comprises 3 mining tenements and 3 exploration
tenements that host high-quality kaolin deposits,
containing naturally occurring kaolinite plates and
halloysite tubes.
The GWP is development-ready, with all key
approvals for commencement of construction,
feasibility studies completed, and 4 binding offtake
agreements finalised for the initial Stage 1A+
development for nominal production of 100,000 wet
metric tonnes per annum (wmt pa).
The project funding process is well-advanced,
with development subject to funding and a final
investment decision.
Figure 1 - The Great White Project regional
location map.
Project funding
During FY26, the Company progressed its strategy
to secure the balance of funding required to
support a final investment decision for the GWP’s
initial Stage 1A+ development of (FID), alongside the
$75 million debt facility previously credit-approved
by Merricks Capital.
This included engagement with a Middle East-
based cornerstone investor for a proposed asset
level investment covering both the GWP and the
HPA Project. Due diligence on the investment
by the cornerstone investor was completed
and negotiations on key commercial terms and
documentation had reached final stages, before
being interrupted due to the ongoing geopolitical
developments in the Middle East.
The Company continues to assess a range of
alternative funding, strategic and corporate
opportunities to unlock value from the GWP.
Following the progress achieved and capital
discipline maintained during Early Works activities
(see Early Works section on page 17), the balance of
equity funding required to reach a final investment
decision for the development of Stage 1A+ (FID)
was reduced to approximately $40 million12
.
Commercial strategy
12
This estimate is indicative only and subject to change due to
economic conditions, funding structure assumptions and the proposed
arrangements with Merricks Capital. The estimate does not factor in the
potential impacts of recent geopolitical events, including possible effects
on diesel pricing or availability.
Annual Report 2026 13
Andromeda’s commercial strategy has identified
a product portfolio of high-quality kaolin products
able to command premium pricing, in growing
established markets. This includes:
• Great White CRM™ and Great White KCM™90
which were determined to be high value
products in the established and growing
markets for high-quality large-format ceramic
tiles and slabs, and porcelain tableware
• Great White HRM™ is identified as a
complementary product, which requires further
customer product validation which is being
undertaken. The identified uses of Great White
HRM™ are as a rheology modifier and as an
additive in the global market for low-carbon
concrete production.
The commercial strategy also identified the
significant opportunity to further beneficiate GWP’s
kaolin products to produce the critical mineral
high-purity alumina (HPA) and for this to become
a high-value accretive complementary product
(see HPA Project section on page 21). Andromeda’s
core products are ideally suited for, and targeted
at, the high-quality ceramic tiles and slabs, and
porcelain tableware market segments. These
market segments are large and established, where
customers require the quality of kaolin products to
be maintained consistently over time.
Table 1 - Andromeda’s core and complementary
product portfolio
Product Description End-use markets
CORE
Great White
CRM™P
Fully refined ultra-fine dried
kaolin product with high
brightness.
Optimised for use in high-quality porcelain
tableware.
Great White
CRM™T
Fully refined ultra-fine dried
kaolin product with high
brightness and high alumina
content.
Optimised for use in high-quality ceramic
tiles and slabs.
Great White
KCM™90
Refined, bright white kaolin
product.
For use in ceramics and can also be used
to improve lower grade resources to
increase the total value of the resultant
combined product, for use in other industry
applications.
COMPLEMENTARY
Great White
HRM™
Concrete additive to reduce
carbon
Optimised for use as a cement additive in
the production of low-carbon concrete.
Highly reactive halloysite-
kaolin rheology modifier
High solids slurries including concrete and a
large range of associated applications where
its suspension properties are very effective.
High-Purity
Alumina (HPA)
Beneficiation of GWP kaolin
products into the critical
mineral HPA
Light-emitting diode lighting (LEDs), Lithium-
ion batteries semi-conductors, and other
high-performance technologies
Figure 2 - Images show (from left) kaolin clay from Andromeda’s GWP, which is then refined and
Andromeda Metals Limited
14
processed, before being graded and packaged into various products that meet our clients’ exacting
specifications.
Target markets Target segments
Europe
Key markets –
Spain & Italy
High-end
ceramics: tiles
and countertops
Spain
#1 importer of kaolin1
#7 ceramic tile producer2
#3 exporter of ceramic tiles3
Italy
#4 importer of kaolin1
#8 ceramic tile producer2
#4 exporter ceramics tiles3
Countertops4
US$160 billion global market
opening to porcelain slabs due to
silicosis risk
Stage 1A+ path to market
Binding offtakes with IberoClays
and Traxys
Asia Pacific
Key markets –
India & Japan
High-end
ceramics – tiles,
tableware and
countertops
India
#9 importer of kaolin1
#2 ceramic tile producer (14% CAGR)2
#2 exporter of ceramic tiles3
Japan
#3 importer of kaolin1
Leading high-end porcelain
tableware producer6
Countertops4
As above – US$160 billion global
market opening to porcelain
slabs due to silicosis risk
Stage 1A+ path to market
Binding offtakes with Plantan
Yamada and Traxys
China A broad range
of high-end
applications via
distribution
Largest market
#1 consumer of kaolin
#2 importer of kaolin1
#1 ceramic tile producer2
#1 exporter ceramic tiles2
Deep high end-market
Multiple applications
High long-term growth5
Kaolin imports CAGR of 3.3% to
2041
Stage 1A+ path to market
Binding offtake with Foshan
Gaoming
1. Based on World Bank data.
2. World production and consumption of ceramic tiles, 14th Edition (MECS/Acimac) September 2026
3. Top 10 countries for ceramic tile exports in 2018-2022 in million square metres, and Compound Annual Growth Rate (CAGR) 2018-22, Baraldi, 2023.
4. Global Countertop Industry Report, Freedonia Group, March 2023.
5. HQ Kaolin Market Study, TZMI, 2025.
6. Kaolin consumption by leading tableware manufacturers in Asia (excluding China), Hart, 2021.
Annual Report 2026 15
To support premium pricing of kaolin products
from GWP into these segments, an extensive series
of product validation work and trials have been
conducted.
Successful product validation programs require
credible independent institutions and/or potential
offtake partners with the requisite industry
expertise, capability, with the requisite equipment
to test and validate the high-quality and value in
use of Andromeda’s products.
For Great White CRM™ and Great White KCM™90,
this has included:
• Independent test work, international
benchmarking and value in use analysis,
conducted by Spain’s Institute of Technical
Ceramics (ITC);
• Product characterisation and international
benchmarking conducted by IberoClays; and,
• Successful commercial scale pilot plant
ceramic glaze trials.
The product validation program for these products
determined they:
• exhibited world class levels of brightness,
aluminium-to-iron ratios and mechanical
strength when fired;
• represented above-market value in use in
the fast- growing large format porcelain and
ceramic tile and glaze segments13,14
; and,
• supported potential use in the ultra-white and
super-white ceramic slab segments15
.
Further product validation trials were conducted to
extend the use of Great White CRM™ into ceramic
and porcelain glaze formulations10
. The trials
assessed the use of Great White CRM™ in two key
glaze formulation segments:
• a standard glaze composition to manufacture
single-fired wall tiles with a glossy white opaque
finish, with kaolin content of 8.3% by weight; and,
• a matt “smaltobbio” glaze composition for the
manufacture of porcelain tiles, with a kaolin
content of 22%.
The findings of the trials successfully validated
Great White CRM™ as a high-quality kaolin product
for use in industrial glaze formulations, enhancing
Andromeda Metals’ position as a key supplier to
the ceramic industry.
The successful results from the product validation
trials supported products marketing efforts, which
ultimately led to the