Progress of Early Works Activities at Great White Project
Released
Released
Announcement PDF
Progress of Early Works Activities at the Great White Project
Andromeda Metals Limited (ASX: ADN) (Andromeda, the Company) is pleased to provide
the following update on the progress of Early Works activities at the Great White Project (GWP,
the Project).
Planned pre-construction Early Works activities, with their progress status, include:
• Payment of environmental compliance payments ✓Completed
• Site preparation activities, including:
– construction of the mine access, and
– bulk earthworks for the Stage 1A+ processing plant.
✓Completed
Early 2026
• Grade Control Drilling Early 2026
• Geotechnical Drilling ✓Completed
• Insurance arrangements ✓Completed
• Finalisation of the Engineering Detailed Design for:
– the Stage 1A+ processing plant, and
– supporting water infrastructure.
Underway
Underway
• Transport of key long-lead equipment items, currently
fabricated and warehoused overseas, to Australia.
Underway
These Early Works activities are supported by funds raised through the recent $14 million
capital raising (before costs), including $13 million under a Share Placement conducted in
October and $996,000 via a Share Purchase Plan which closed in November1.
LOCAL COMMUNITY INFORMATION SESSIONS
Andromeda is committed to engaging effectively with the community and stakeholders.
During November, information sessions were held at both Poochera and Streaky Bay
enabling Andromeda to engage and inform the local community on the Project and
commencement of Early Works activities.
1
Refer to ADN ASX dated 18 November 2025 titled Results of Share Purchase Plan.
Andromeda Metals Limited ASX: ADN
ASX Announcement
10/431 King William Street
Adelaide, SA 5000
Tel:+61 8 7089 9800
ir@andromet.com.au
24 December 2025
ABN
75 061 503 375
Andromeda Metals Limited | 2
Photos of Community information sessions held at
venues in both Poochera and Streaky Bay.
GWP BOND LODGED ENABLING COMMENCEMENT OF EARLY WORKS
Prior to the commencement of Early Works activities at the Project, lodgement of a $3.79
million rehabilitation bond and payment of $670,000 to the Native Vegetation Fund to satisfy
the Significant Environmental Benefit (SEB) obligations were required2. The rehabilitation
bond is required as part of the South Australian Department for Energy and Mining’s (DEM)
Rehabilitation Financial Assurance, with the SEB payment required as part of the Company’s
compliance with its approved Program for Environment Protection and Rehabilitation (PEPR).
Following satisfaction of these environment compliance obligations, Andromeda was able
to commence Early Works at the GWP.
SITE PREPARATION – CONSTRUCTION OF MINE ACCESS
Set out below are images of site preparation activities, including the construction of mine
access which is now complete, signage which has been erected at the entrance to the mine
site, and various machinery and equipment used during Early Works activities.
Photos of a sign erected at the
entrance to the GWP mine site.
2
Refer ADN ASX dated 24 November 2025 titled GWP Bond Lodged and Early Works Commence.
Andromeda Metals Limited | 3
← ↙ Construction of
mine access, which is
now complete.
→ Fencing machinery
and posts used in
construction of fencing,
which is underway.
↓ Road compactor.
Completed
mine
access
GEOTECHNICAL DRILLING
Geotechnical drilling has been undertaken to better understand subsurface conditions
which in turn inform the detailed engineering design of the Stage 1A+ Processing Plant area.
Andromeda Metals Limited | 4
Machinery and vehicles conducting geotechnical drilling in foreground, with
future pit located in clearing immediately beyond the tree line in top right corner.
Scheduling of the balance of the Early Works activities is expected to commence in early
2026.
While these Early Works are underway, Andromeda is also progressing:
– Finalisation of the Engineering Detailed Design for the both the Stage 1A+ processing
plant and supporting water infrastructure;
– Preparation for the transport of key long-lead equipment items, which are currently
fabricated and warehoused overseas, to Australia; and,
– the funding process for the capital required to support a final investment decision for
Stage 1A+.
To watch a 3D virtual walk-through of the design and layout of the Stage 1A+ Processing
Plant, click the image below.
Andromeda Metals Limited | 5
Sarah Clarke, Andromeda’s Acting Chief Executive Officer said:
“2025 has been a productive year for Andromeda, with the team having worked diligently
advanced the Great White Project, through progressing the detailed design for the Stage
1A+ processing plant, securing funding to enable the commencement of Early Works on site
and the transport of key long-lead equipment items to Australia.
“These activities represent a critical step toward pre-construction readiness for the Project, as
we continue to progress the funding process required to support a final investment decision.
“As another successful year comes to a close, Andromeda’s Board and management would
like to extend our sincere appreciation for the ongoing support and commitment of all our
stakeholders, which has been instrumental in our shared success.
"We look forward to continuing to update you on our future achievements in 2026.”
This announcement has been approved for release by the Board of Andromeda Metals Limited.
For more information about the Company and its projects, please visit our website,
www.andromet.com.au or contact:
Manager, Investor Relations & Corporate Affairs
Patrick Sinclair
T: 08 7089 9819
M: 0403 708 431
E: Patrick.Sinclair@andromet.com.au
FORWARD-LOOKING STATEMENTS
This document contains or may contain certain forward-looking statements and comments about future events, that
are based on Andromeda's beliefs, assumptions and expectations and on information currently available to
management as at the date of this document. Often, but not always, forward-looking statements can generally be
identified by the use of forward-looking words such as "may", "will", "expect", "plan", "believes", "estimate", "anticipate",
"outlook", and "guidance", or similar expressions. Such statements are only expectations or beliefs and are subject to
inherent risks and uncertainties which could cause actual values, results or performance achievements to differ
materially from those expressed or implied in this presentation. Where Andromeda expresses or implies an expectation
or belief as to future events or results, such expectation or belief is expressed in good faith and on a reasonable basis.
No representation or warranty, express or implied, is made by Andromeda that the matters stated in this presentation
will in fact be achieved or prove to be correct. Except as required by law, Andromeda undertakes no obligation to
provide any additional or updated information or update any forward-looking statements, whether on a result of new
information, future events, results or otherwise. Readers are cautioned against placing undue reliance on forward-
looking statements. These forward-looking statements are not guarantees of future performance and involve known
and unknown risks, uncertainties, assumptions and other important factors, many of which are beyond the control of
Andromeda, the directors, and management of Andromeda.