Great White Project Early Works Update
Released
Released
Announcement PDF
Sign-up and log into ADN’s Investor Hub
Great White Project Early Works Update
Andromeda Metals Limited (ASX: ADN) (Andromeda, the Company) is pleased to provide
the following update on the status of on-site Early Works activities at the Great White Project
(GWP) and associated project readiness.
As outlined in the Company Update released on 31 March 2026, Andromeda has
implemented cost-saving measures, including moderating expenditure across certain Early
Works activities, while funding discussions continue.
Since that update, Andromeda has successfully completed its on-site Early Works program.
These Early Works activities have materially progressed the GWP and established a strong
foundation for parallel construction activities.
Further, as a result of the progress achieved and capital discipline maintained during these
Early Works, the balance of equity funding required to reach a final investment decision for
the development of Stage 1A+ (FID) has reduced to approximately $40 million.1 This estimate
remains indicative only and is subject to funding structure, transaction terms and market
conditions. The Company will continue to update the market on the funding process for the
GWP as material developments occur, in accordance with its continuous disclosure
obligations.
Outlined below is a summary of the planned pre-construction Early Works and associated
activities, with their progress status:
• Payment of environmental compliance payments Completed
• Site preparation activities, including:
– construction of the mine access, and
– bulk earthworks for the Stage 1A+ processing plant.
– Establishment of hardstand for roads, processing
facility and administration
Completed
Completed
• Grade Control Drilling Completed
1
This estimate is indicative only and subject to change due to economic conditions, funding structure assumptions and the
proposed arrangements with Merricks Capital. The estimate does not factor in the potential impacts of recent geopolitical
events, including possible effects on diesel pricing or availability.
Andromeda Metals Limited ASX: ADN
ASX Announcement
10/431 King William Street
Adelaide, SA 5000
Tel:+61 8 7089 9800
ir@andromet.com.au
15 April 2026
ABN
75 061 503 375
Andromeda Metals Limited | 2
• Geotechnical Drilling Completed
• Insurance arrangements Completed
• Finalisation of the Engineering Detailed Design for:
– the Stage 1A+ processing plant, and
– supporting water infrastructure.
Progressed; now on
hold
• Transport of key long-lead equipment items, currently
fabricated and warehoused overseas, to Australia.
Progressed/Underway
Early Works activities
Prior to any ground engaging activities to develop the GWP the Company lodged a $3.79
million rehabilitation bond and paid $670,000 to the Native Vegetation Fund to satisfy the
Significant Environmental Benefit (SEB) obligations. Completion of these requirements allows
any further works to be undertaken at the GWP under the approved Mining Lease.
The Early Works program was designed to establish site access and create a hardstand area
to enable to efficient progression of subsequent construction activities. Early Works included
the approved removal and mulching of vegetation, collection of the mulch and topsoil for
future rehabilitation and the establishment of the mining boundary with fencing. The mine
access track was established and sheeted with site sourced calcrete to create an all-
weather access. Following clearance of the processing plant area, geotechnical drilling was
undertaken to inform the detailed foundation design. This work then allowed for the planned
bulk earthworks to create the hardstand for the Stage 1A+ processing plant and associated
infrastructure.
Early Works completed to date include site clearance, stockpiling of topsoils, establishment
of the mine access track, fencing and site signage, excavation of stormwater pond,
formation of processing plant hard stand, processing road ways and stormwater
management, establishment of a laydown area for Long Lead Items (LLI) and completion of
a detailed drilling program for grade control. These programs of work had to be undertaken
sequentially, meaning that one task needed to be undertaken before the consecutive task.
Completion of this Early Works program establishes the site for construction and enables
future construction activities to be undertaken across multiple work fronts, supporting a more
efficient construction schedule once funding is in place.
Andromeda Metals Limited | 3
GWP mine access track leading to Stage 1A+ Processing Plant area
Bulk
earthworks
in progress
Click on the following image to
watch a video showing the
progress of bulk earthworks at
the Great White Project.
Andromeda Metals Limited | 4
As part of the cut and fill bulk earthworks program, areas of hard calcrete cap were encountered on
site, most notably within the storm water pond area, which was designed as a two-metre-deep
stormwater catchment.
To improve productivity and provide a borrow pit for capping rock, the stormwater pond area was
drilled and blasted.
The drill-and-blast program was executed successfully and delivered a material improvement in
excavation productivity. It also provided valuable operational experience in engaging specialist
contractors to drill, load and blast material under site conditions and reliable cost and schedule data
to inform any future drill-and-blast requirements during construction.
Blast guards securing the blast exclusion zone
Controlled blasting taking place
Andromeda Metals Limited | 5
Inspection of blast area following blasting Excavation of blast area following blasting
The Early Works completed to date have successfully established the Great White site. In doing so they
have advanced the Project, reduced construction risk and positioned the Great White Project to
transition efficiently into the construction phase should funding arrangements be finalised.
In addition to the physical works, the Early Works program enabled confirmation of geotechnical
conditions to finalise key aspects of engineering. Commencement of on-site works has also provided
the Company with early insight into planning, systems contractor engagement and execution,
invaluable experience for future project delivery.
Grade control drilling
Following the successful completion of grade control drilling, preparation of drillhole samples has
commenced at the Streaky Bay Pilot Plant. Analysis and assessment of the samples will inform updates
to the resource model, starting pit design and short-term mine planning.
Images of grade control drilling during Early Works
Transportation of long lead equipment items
The transportation of key long lead equipment items, which are currently fabricated and warehoused
overseas, to Australia is underway.
Andromeda Metals Limited | 6
The current status of long-lead equipment items is as follows:
Long lead
equipment item
Fabrication Status Transportation Status
Fluid bed dryer Factory acceptance testing
(FAT) completed.
Enroute to Australia.
Thickener FAT completed. Arrived and stored in Australia.
Filter Press FAT completed. Arrived and stored in Australia, except for
break-bulk components awaiting departure
of suitable vessel.
Drum washer FAT completed; warehoused. Planned to be in line with project schedule.
Filter Cake
Feeder
Engineering design complete;
fabrication to commence
following an anticipated FID.
Planned to be in line with project schedule.
Sarah Clarke, Andromeda’s Acting Chief Executive Officer said:
“The Early Works program has delivered tangible value beyond site establishment — validating key
design assumptions, materially improving project readiness and enabling a more efficient construction
schedule. Importantly, the completion of these Early Works has also reduced the balance of equity
now required to reach a final investment decision for Stage 1A+ of the Great White Project.”
Sue-Ann Higgins, Andromeda’s Executive Chair, said:
“The Board acknowledges the efforts of the Andromeda team in successfully concluding the Early
Works program and thanks them for their ongoing high quality work and dedication.”
This announcement has been approved for release by the Board of Andromeda Metals Limited.
For more information about the Company and its projects, please visit our website,
www.andromet.com.au or contact the Company on ir@andromet.com.au
FORWARD-LOOKING STATEMENTS
This document contains or may contain certain forward-looking statements and comments about future events, that
are based on Andromeda's beliefs, assumptions and expectations and on information currently available to
management as at the date of this document. Often, but not always, forward-looking statements can generally be
identified by the use of forward-looking words such as "may", "will", "expect", "plan", "believes", "estimate", "anticipate",
"outlook", and "guidance", or similar expressions. Such statements are only expectations or beliefs and are subject to
inherent risks and uncertainties which could cause actual values, results or performance achievements to differ
materially from those expressed or implied in this presentation. Where Andromeda expresses or implies an expectation
or belief as to future events or results, such expectation or belief is expressed in good faith and on a reasonable basis.
No representation or warranty, express or implied, is made by Andromeda that the matters stated in this presentation
will in fact be achieved or prove to be correct. Except as required by law, Andromeda undertakes no obligation to
provide any additional or updated information or update any forward-looking statements, whether on a result of new
information, future events, results or otherwise. Readers are cautioned against placing undue reliance on forward-
looking statements. These forward-looking statements are not guarantees of future performance and involve known
and unknown risks, uncertainties, assumptions and other important factors, many of which are beyond the control of
Andromeda, the directors, and management of Andromeda.