Andromeda expansion plans for The Great White Project
Released
Released
Announcement PDF
6 May 2024
Andromeda Metals Limited ASX: ADN
ASX Announcement
10/431 King William Street
Adelaide, SA 5000
Tel:+61 8 7089 9800
admin@andromet.com.au
ABN
75 061 503 375
Andromeda expansion plans for The Great White Project
•
Expansion plans for the GWP brought forward due to anticipated sales volumes
•
Planned production of new Stage 1A+ for 90,000 tpa (from previous planned 50,000 tpa)
•
Pre-tax NPV of the GWP increased by A$64M
Andromeda Metals Limited (ASX: ADN) (Andromeda, the Company) is pleased to announce that it has
taken the decision to bring forward expansion plans for The Great White Project (TGWP).
Anticipated sales volumes for TWGP’s kaolin products under binding agreements currently exceed the
planned production of 50,000 tonnes per annum (tpa) under the initial Stage 1A 1 of the project, as
contemplated in the 2023 Definitive Feasibility Study (2023 DFS). The Company expects these binding
volumes to be increased through the conversion of volumes under our existing Heads of Agreement (HOA),
negotiations for which have now reached an advanced stage.
Given this position, the Company has taken the decision to bring forward the staged expansion of the
project to reach cumulative nominal kaolin production of 90,000 tpa (100,000 wet metric tpa) (Stage 1A+)
within 17 months of final investment decision (FID).
This has further led to the Company’s decision to reschedule subsequent stages of the 2023 DFS, such that
the expansion to TGWP’s ultimate 300,000 tpa will now proceed as follows:
Stage 1A+
Stage 1B
Stage 2
Total
Nominal kaolin production (dmt 2)
90,000 tpa
100,000 tpa
110,000 tpa
300,000 tpa
Nominal kaolin production (wmt 3)
100,000 tpa
~110,000 tpa
~120,000 tpa
~330,000tpa
Construction start (months from FID)
0 months
12 months
30 months
n/a
First shipment (months from FID)
17 months
24 months
42 months
n/a
Full production (months from FID)
23 months
30 months
48 months
n/a
A comparison of the new staging to the prior staging is shown in the chart below.
Refer to ADN ASX dated 24 August 2023 titled The 2023 DFS delivers significantly improved economics…
dmt = dry metric tonnes
3
wmt = Wet metric tonnes (product specification which allows for up to 12% moisture)
1
2
2023 DFS Capacity vs 2023 DFS Rescheduled Capacity
As noted, the decision follows the progress made in negotiations with current and potential offtake
partners, including Traxys 4. The Company now anticipates total volumes committed under binding offtake
agreements to surpass nominal Stage 1A capacity from Year 1 and reach 100,000 wet metric tpa of kaolin
in Year 3.
TGWP Production and Offtake Profile
Refer to 1) ADN ASX dated 21 November 2023 titled Non-binding Heads of Agreement signed with Traxys 4 2) Refer to ADN
ASX dated 9 November 2023 titled Heads of Agreement signed for Indian and global markets.
4
Andromeda Metals Limited | 2
The above volumes include anticipated commitments for Great White CRM™ and Great White KCM™,
which target the high-value ceramic tile/countertop and porcelain tableware markets. Volume
commitments for Great White HRM™ have been excluded and, subject to end user testing, will support
future expansion opportunities.
All material assumptions used in the 2023 DFS 5 continue to apply and have not materially changed.
Forecasts are based on TGWP 2022 Ore Reserve Estimate 6. The pre-tax NPV (8) of TGWP has increased by
A$64 million due to the revenues brought forward by the re-scheduling of the expansion stages.
Pre-tax NPV (8) (real)
2023 DFS
Re-staged 2023 DFS
$1,010 million
$1,074 million
In re-staging TGWP, Andromeda has assessed the economic impact of each Stage of development, as
summarised below. The results of this analysis are shown on a pre and post-tax basis in the figures below.
As noted above, all material assumptions used in the 2023 DFS 7 continue to apply and have not materially
changed.
Pre-tax NPV (8) (real) of each Stage of TGWP
Refer to ADN ASX dated 24 August 2023 titled The 2023 DFS delivers significantly improved economics…
Information that relates to Mineral Resource Estimate has been previously announced to ASX on 26 November 2020,
"Updated Mineral Resource for the Great White Kaolin Project" and, information that relates to Ore Reserve Estimate has
been previously announced to ASX on 6 April 2022, "Great White Kaolin Project –Definitive Feasibility Study and Updated Ore
Reserve" both available at https://www2.asx.com.au/markets/company/adn. Andromeda confirms that it is not aware of any
new information or data that materially affects the information included in the original market announcement and that all
material assumptions and technical parameters underpinning the estimates continue to apply and have not materially
changed.
7
Refer to ADN ASX dated 24 August 2023 titled The 2023 DFS delivers significantly improved economics…
5
6
Andromeda Metals Limited | 3
Post-tax NPV (8) (real) of each Stage of TGWP
Bob Katsiouleris, Andromeda’s CEO and Managing Director said:
“The decision to increase the scale of our planned Stage1A+ operation is a significant step forward in
Andromeda’s commercial strategy, which greatly improves capital efficiency and financial outcomes,
and support the ongoing discussions with the numerous debt providers currently underway.”
This announcement has been approved for release by the Board of Directors of Andromeda Metals Limited.
This announcement contains certain forward-looking statements and comments about future events, that are based on
Andromeda's beliefs, assumptions and expectations and on information currently available to management as at the date of
this announcement. Forward looking statements may include, without limitation, statements regarding plans, strategies and
objectives of management, anticipated production and production potential, financial forecasts, product quality estimates of
future Mineral Resources and Ore Reserves. Such statements are only expectations or beliefs and are subject to inherent risks and
uncertainties which could cause actual values, results or performance achievements to differ materially from those expressed or
implied in this announcement. Readers are cautioned against placing undue reliance on forward-looking statements. These
forward-looking statements are not guarantees of future performance and involve known and unknown risks, uncertainties,
assumptions and other important factors, many of which are beyond the control of Andromeda, the directors, and
management of Andromeda.
For more information about the Company and its projects, please visit our website,
www.andromet.com.au or contact:
Manager, Investor Relations & Corporate Affairs