IMARC Presentation
Released
Released
Announcement PDF
Andromeda
IMARC Conference
Sydney
29 October 2026
ASX:ADN
andromet.com.au
Level 10, 431 King William Street, Adelaide, South Australia 5000
+61 8 7089 9800
Authorised for release by the Board of Directors of Andromeda Metals Ltd
This presentation contains summary information about Andromeda, and its activities current only at the date of this
presentation. This presentation is for information purposes only. The information in the presentation is of a general nature only
and does not purport to be complete. This presentation should be read in conjunction with Andromeda’s most recent
financial report and other periodic and continuous disclosure announcements lodged with the Australian Securities Exchange
(ASX) which are available at www.asx.com.au and also available on Andromeda’s website at www.andromet.com.au.
No investment or financial product advice
The information contained in this presentation does not constitute investment advice or financial product advice (nor
taxation or legal advice) and is not intended to be used as the basis for making an investment decision or as a
recommendation to acquire securities in Andromeda. The information contained in this presentation should not be relied
upon as a recommendation or forecast by Andromeda (including as to the performance of Andromeda or its share
price). Readers should obtain their own professional advice and carry out their own independent investigations and
assessment of the information in this presentation (including any assumptions) before acting.
This presentation has been prepared without taking into account any particular person’s objectives, financial situation or
needs; does not purport to identify the nature of specific market or other risks associated with any investment in the
Company and does not constitute any legal, taxation, investment or accounting advice. An investment in Andromeda's
securities is subject to investment and other known and unknown risks, some of which are beyond the control of Andromeda,
including loss of income and principal invested. The Company does not guarantee any particular rate of return or the
performance of the Company nor does it guarantee any particular tax treatment. Any investment decision should be based
only on a person's own due diligence, inquiry, assessment and professional advice.
Forward-looking statements
This presentation contains or may contain certain forward-looking statements and comments about future events, that are
based on Andromeda's beliefs, assumptions and expectations and on information currently available to management as at
the date of this presentation.
Often, but not always, forward-looking statements can generally be identified by the use of forward-looking words such as
"may", "will", "expect", "plan", "believes", "estimate", "anticipate", "outlook", and "guidance", or similar expressions, and may
include, without limitation, statements regarding plans, strategies and objectives of management, anticipated production
and production potential, financial forecasts, product quality estimates of future Mineral Resources and Ore Reserves.
Such statements are only expectations or beliefs and are subject to inherent risks and uncertainties which could cause actual
values, results or performance achievements to differ materially from those expressed or implied in this presentation. Where
Andromeda expresses or implies an expectation or belief as to future events or results, such expectation or belief is expressed
in good faith and on a reasonable basis. No representation or warranty, express or implied, is made by Andromeda that the
matters stated in this presentation will in fact be achieved or prove to be correct. Except as required by law, Andromeda
undertakes no obligation to provide any additional or updated information or update any forward-looking statements,
whether on a result of new information, future events, results or otherwise.
Readers are cautioned against placing undue reliance on forward-looking statements. These forward-looking statements are
not guarantees of future performance and involve known and unknown risks, uncertainties, assumptions and other important
factors, many of which are beyond the control of Andromeda, the directors, and management of Andromeda. These factors
include, but are not limited to difficulties in forecasting expected production quantities, the potential that any of
Andromeda’s projects may experience technical, geological, metallurgical and mechanical problems, changes in market
prices and other risks not anticipated by Andromeda, changes in exchange rate assumptions, changes in product pricing
assumptions, major changes in mine plans and/or resources, changes in equipment life or capability, emergence of
previously underestimated technical challenges, increased costs, and demand for production inputs.
Not an offer
This presentation is for information purposes and is not, and does not purport to be, a prospectus, product disclosure
statement or any other offering document under Australian law or the law of any other jurisdiction. The information does not
and will not constitute or form part of an offer, invitation, solicitation or recommendation in relation to the subscription,
purchase or sale of securities in any jurisdiction. The distribution of this presentation in jurisdictions outside Australia may be
restricted by law and you should observe any such restrictions.
No warranty
While care has been taken in preparing the information in this presentation, no representation or warranty, express or implied,
is made as to the currency, accuracy, reliability, completeness or fairness of the information, opinions and conclusions
contained in this presentation. The information in this presentation has been obtained from or based on sources believed by
Andromeda to be reliable. This includes references to test results and reports completed by external parties.
Information in this presentation which is attributed to, or derived from, a third-party source has not been independently checked or
verified by Andromeda. No representation or warranty is made as to the accuracy, completeness or reliability of such information. This
includes information relating to market data for kaolin or HPA, including forecast pricing, forecast supply and demand and market
segments and end markets.
To the maximum extent permitted by law, neither Andromeda nor its related corporations, Directors, officers, employees, advisers or
agents, nor any other person, accepts any liability, including, without limitation, any liability arising from the use of this presentation or its
contents or otherwise arising in connection with them, nor guarantees or makes any representations or warranties, express or implied, as
to or takes responsibility for, the currency, accuracy, reliability, completeness or fairness of this presentation nor the information, opinions
and conclusions contained in this presentation.
Assumptions and Notes for Financial Information on 2023 DFS and Stage 1A+ in this presentation:
Further details on the 2023 DFS and the assumptions and notes for the 2023 DFS (and risk factors applicable to the Company)can be
found in the Company’s ASX Announcement ‘2023 Definitive Feasibility Study Results’ released on 24 August 2023. This should be read
together with ASX Announcement dated 6 May 2024 “Andromeda expansion plans for The Great White Project” and “Clarification of
expansion plans for The Great White Project” and the ore reserve estimate previously announced to ASX on 6 April 2022, "Great White
Kaolin Project –Definitive Feasibility Study and Updated Ore Reserve".
Andromeda confirms that it is not aware of any new information or data that materially affects the information included in the original
market announcements and that all material assumptions and technical parameters underpinning the estimates and financial
information continue to apply and have not materially changed.
Assumptions and Notes for Financial Information on the HPA Scoping Study in this presentation:
Further details on the HPA Scoping Study and the material assumptions, modifying factors and Cautionary Statement for the HPA
Scoping Study (and risk factors applicable to the HPA Project) can be found in the Company’s ASX Announcement ‘Results of HPA
Scoping Study’ released on 18 September 2025.
Andromeda confirms that it is not aware of any new information or data that materially affects the information included in the original
market announcements and that all material assumptions and technical parameters underpinning the estimates and financial
information continue to apply and have not materially changed.
Currency
Unless otherwise stated, all cashflows in this presentation are in Australian dollars, are undiscounted and are in real terms (not subject to
inflation/escalation factors).
Mineral Resources and Ore Reserve Estimates
Information that relates to Ore Reserve Estimate has been previously announced to ASX on 6 April 2022, "Great White Kaolin Project –
Definitive Feasibility Study and Updated Ore Reserve. Andromeda confirms that it is not aware of any new information or data that
materially affects the information included in the original market announcement and that all material assumptions and technical
parameters underpinning the estimates continue to apply and have not materially changed.
Andromeda confirms that it is not aware of any new information or data that materially affects the information included in the original
market announcements and that all material assumptions and technical parameters underpinning the estimates continue to apply and
have not materially changed.
Competent Person's Statements
The data in the HPA Scoping Study that relates to Ore Reserve Estimates for the Great White Deposit is based on, and fairly represent,
information and supporting documentation fully reviewed and understood by Mr Joseph Ranford who is a Fellow of the Australasian
Institute of Mining and Metallurgy (FAusIMM). Mr Ranford approves the Ore Reserve Estimates for the Great White Deposit. Mr Ranford is
the Chief Operating Officer of Andromeda Metals Limited and has sufficient experience relevant to the style of mineralisation and type
of deposit under consideration, and to the activity which he is undertaking, to qualify as a Competent Person as defined in the 2012
Edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (the “JORC Code”). Mr
Ranford consents to the information contained in this report being used in the form and context in which it appears. Mr Ranford holds
Shares and Performance Rights in the Company and is entitled to participate in Andromeda’s employee incentive plan.
Disclaimers and Important Information
ASX:ADN | andromet.com.au Andromeda Metals Ltd | IMARC Conference 2026 2
ASX:ADN | andromet.com.au Andromeda Metals Ltd | IMARC Conference 2026 3
Andromeda is advancing two high-value projects, leveraging its high-quality kaolin resource
Development ready industrial minerals platform with pathway into critical minerals
The Great White Project: development ready
1 2 High Purity Alumina Project: patented process
Australia’s Next Leading Industrial & Critical Minerals Company
ASX:ADN | andromet.com.au Andromeda Metals Ltd | IMARC Conference 2026 4
Andromeda’s Competitive Advantages
One high-quality resource | Two significant value opportunities
The Great White Project
Delivering premium kaolin products for use in high-end ceramics
High Purity Alumina (HPA) Project
Unlocking Critical Minerals from a High–Quality Kaolin Resource
Development Ready
All key permits in place for construction to commence
Early Works completed & key long lead equipment items built
and in storage in Australia
Binding Offtakes
100% of Stage 1A+ planned production covered by binding
offtakes by year 3
Robust Economics
A$763M post-tax NPV8; 43% IRR; A$140M p.a. average EBITDA
over LOM over for 28-year mine life1
Pathway to Development
Actively assessing a range of funding, strategic and corporate
opportunities to unlock value from the Great White Project,
supported by a credit-approved A$75 million debt facility.2
High-quality feedstock
Great White kaolin is naturally high in alumina and has low
levels of deleterious impurities
Proprietary process
8+ years spent developing innovative process to produce
HPA and Smelter Grade Alumina
Testwork underway
Producing commercial samples of 4N+ HPA for potential
customers and assessment of by-product value-add potential
Tier 1 mining jurisdiction: Located in South Australia which is ranked #4 globally in Investment Attractiveness Index5
Notes:(1) Refer to ASX ADN 24 August 2023 titled 2023 Definitive Feasibility Study Results. All material assumptions and technical parameters underpinning the estimates and
forecast financial information continue to apply and have not materially changed. (2) Refer to ADN ASX 4 June 2025, titled Credit Approved A$75 Million Debt Facility, (3)
Refer to ADN ASX 6 October 2025, titled Andromeda granted first patent for proprietary HPA process. (4) Refer to ADN ASX 29 October 2026 – Andromeda Produces 4N+ HPA
to 99.9989% Purity and Send Inaugural Sample to Japan for Customer Evaluation . (5) Annual Survey of Mining Companies for 2025, Fraser Institute (February 2026)
HPA process Patented3
Flexible flowsheet can produce HPA in a wide range of
product forms and proven at pilot-scale to 99.9989% purity4
ASX:ADN | andromet.com.au Andromeda Metals Ltd | IMARC Conference 2026 5
Overview of Offtakers
Notes (1) Refer ADN ASX dated 8 June 2023 titled Binding Offtake Agreement signed for Japanese market. (2) Refer ADN ASX dated 18 October 2023 titled Binding Offtake
Agreement signed for Chinese market, adjusted per Seller’s volume option for Year 3. (3) Refer ADN ASX dated 19 January 2024 titled Binding Sales and Distribution Agreement
Signed with IberoClays. (4) Refer ADN ASX dated 17 July 2024 titled Binding Offtake Agreement signed with Traxys. (5) Volumes exclude contracted volumes for Great White HRMTM.
GWP Stage 1A+ supported by Binding Offtakes
100% of planned production committed under binding offtake contracts
0
10,000
20,000
30,000
40,000
50,000
60,000
70,000
80,000
90,000
100,000
Year 1 Year 2 Year 3
Wet metric tonnes per annum
Plantan Yamada Foshan Gaoming IberoClays Traxys
1 2 3 4
Ongoing contracted volumes>>
Stage 1A+ nominal
production capacity
Offtaker Markets
Europe
Southeast Asia
Europe
Japan
Foshan Gaoming
China
Binding Offtake Agreements support Stage 1A+
production capacity5
ASX:ADN | andromet.com.au Andromeda Metals Ltd | IMARC Conference 2026 6
Great White Project Early Works Complete
STATUS OF PLANNED ACTIVITIES
Environmental compliance
payments
$3.79M rehabilitation bond lodged with DEM plus $670,000 SEB
payment to the Native Vegetation Fund satisfies the
precondition to starting site works1
Complete
Site preparation, mine access
Construction of the mine access road completed, with site
signage erected at the mine entrance2 Complete
Bulk earthworks
Bulk earthworks for the Stage 1A+ processing plant, including
controlled blasting, and hardstand established for road,
processing facility and administration2,3
Complete
Grade control drilling Drilling completed to confirm ore definition for short term mine
planning3 Complete
Geotechnical drilling Undertaken to better understand subsurface conditions,
informing plant foundation and infrastructure design3 Complete
Insurance arrangements Project insurance arrangements finalised3
Complete
Transport of long-lead
equipment
Key long-lead items are now stored in Australia4
Complete
Engineering Detailed Design
Detailed design for the Stage 1A+ processing plant and
supporting water infrastructure — progressed, currently paused3 Paused
WHAT THIS DE-RISKS
• Great White site established and construction schedule de-
risked3
• Valuable operational experience gained under actual site
conditions3
• Key long-lead equipment fabricated and stored in Australia4
• Balance of equity required for FID reduced to approximately
$40 million, alongside the credit-approved A$75 million Merricks
Capital debt facility3,5
Stage 1A+ Processing Plant
A computer generated image of a plant
Click the image to watch a 3D virtual walk-through of the Stage 1A+ Processing Plant design and
layout
References — Andromeda Metals Limited (ASX: ADN) ASX announcements: (1) GWP Bond Lodged and Early Works Commence, 24 November 2025. (2) Progress of Early
Works Activities at the Great White Project, 24 December 2025. (3) Great White Project Early Works Update, 15 April 2026. (4) Early Works Update — Transport of Long Lead
Items Complete, 6 July 2026. (5) Credit Approved A$75 Million Debt Facility, 4 June 2025.
A De-Risked, Development-Ready Project
ASX:ADN | andromet.com.au Andromeda Metals Ltd | IMARC Conference 2026 7
Great White Project is Construction Ready
Early Works – Site prepared & key long lead items stored in Australia
✓ Early Works excavation
✓ Processing Plant Pad prepared ahead of construction
✓ Grade control drilling
ASX:ADN | andromet.com.au
✓ Freehold land purchased
✓ Drum washer ✓ Thickener ✓ Centrifuge
✓ Fluid bed dryer
✓ Stage 1A Filter press
✓ Engineering design
ASX:ADN | andromet.com.au Andromeda Metals Ltd | IMARC Conference 2026 8
HPA Project
What differentiates Andromeda’s patented process
Kaolin-based production with low cost and low carbon2
Kaolin feedstock
Secure, scalable supply
Low cost
Low cost of production and capital
expenditure
Low carbon
Reduced footprint versus conventional methods
Conventional Aluminium Alkoxide
Process
✕
Aluminium metal feedstock
Refined from aluminium metal through
multiple energy intensive steps
✕
Energy and carbon intensive
Extra stages add cost, energy and
embedded emissions
✕
✕
Complex plant design
Reaction + solvent recovery systems
Andromeda's kaolin-based
process
✓
No aluminium metal inputs
Refined Great White kaolin feedstock1
✓
Market leading economics
Potential to become a leading global
producer of low-cost low carbon HPA2
✓
Tailored to the application
Product forms from amorphous to crystalline
(gamma to alpha)3
✓
Quality Australian supply
Vertically integrated from resource to refined
product
Notes (1) Refer to ADN ASX dated 1 May 2025 titled Andromeda Achieves HPA Breakthrough: Successful Production of 4N HPA & Validation of Novel Flowsheet (2) Refer to ADN ASX dated 18
Sept 2025 titled Results of HPA Scoping Study; all material assumptions and technical parameters underpinning the estimates and forecast financial information continue to apply and have not
materially changed. (3) Refer to ADN ASX dated 7 October 2025 titled HPA Project – Next Phase of Commercialisation Underway. (4) High Purity Alumina Special Report, CRU, October 2025.
Concentrated supply
Around 75% of global supply comes from
China4
ASX:ADN | andromet.com.au Andromeda Metals Ltd | IMARC Conference 2026 9
4N HPA Achieved at Continuous Pilot Scale
Independent analysis confirms 4N+ HPA purity produced from Great White kaolin
99.9989%1
Measured HPA purity
Independently verified by EAG Eurofins (GDMS)
4N+ achieved
Above the 99.99% Al2O3 threshold
Purity confirmed above the 4N threshold
across test methods
Co-products
Amorphous silica under assessment
Silica samples submitted for analysis
Milestone highlights
✓
4N+ HPA pilot scale
Continuous pilot plant produced 4N+ HPA from Great White kaolin, scaling up
from lab production, independently verified to 99.9989% purity1
✓
Inaugural Sample Sent For Customer Evaluation
First sample sent to Japan for customer evaluation by high-tech manufacturer1
✓
Patent granted in South Africa
First patent granted in broad portfolio of national patent applications2
✓
Australian Critical Minerals Prospectus
Included in 2026 Critical Minerals Prospectus3
Next steps and opportunity
✓
✓
US HPA market entry
Non-binding Heads of Agreement signed with Traxys North America to
support Andromeda’s entry into the US HPA market5
➜
Planning Pre-feasibility study (PFS)
Engineering, design and operating data generated to support the next
phase of technical studies
➜
Structural supply deficit emerging
Global 4N+ supply deficit forecast to exceed 127% of demand by 2030, with
~75% of supply currently sourced from China4
Notes: (1) Refer to ADN ASX 29 October 2026 — Andromeda Produces 4N+ HPA to 99.9989% Purity and Send Inaugural Sample to Japan for Customer
Evaluation . (2) Refer to ADN ASX 6 October 2025, titled Andromeda granted first patent for proprietary HPA process. (3) Refer to Australian Critical Minerals
Prospectus. (4) High Purity Alumina Special Report, CRU, October 2025. (5) ADN ASX 19 August 2026 — Strategic HPA Supply HOA with Traxys.
Customer evaluation samples
Production of commercial 4N HPA samples underway, with deliveries
expected through Q4 2026 for prospective customer evaluation programs
ASX:ADN | andromet.com.au Andromeda Metals Ltd | IMARC Conference 2026 10
Advancing Andromeda’s HPA Commercialisation Pathway
STRATEGIC MILESTONE
Non Binding Heads of Agreement signed with Traxys North America1
5-year
Potential sales agency
agreement
2,000 tpa
of HPA targeted under the
agreement
~US$40M2
Indicative annual
sales potential
US market
Supporting US Critical Mineral
Supply Chain initiative
Andromeda & Traxys will work together to:
▪ Develop a targeted US go-to-market strategy
▪ Facilitate the introduction of Andromeda to Project Vault
with the aim of securing sales contracts
▪ Facilitate introductions to other US-based customers and
strategic partners
▪ Support HPA qualification and market entry into the US
US Government’s Project Vault1
▪ Launched in February 2026
▪ Aims to establish a US$12 billion Strategic Critical Minerals Reserve
to strengthen supply chain security and reduce reliance on
China-dominated supply chains
▪ HPA designated as a Critical Mineral in the USA3
Notes (1) Refer ADN ASX announcement dated 19 August 2026 titled Andromeda Signs Strategic HPA Supply HOA with Traxys. (2) Based on indicative pricing of US$20,000 per
tonne assumed under Andromeda’s HPA Scoping Study. (3) High-Purity Alumina is included under Aluminium in the United States’ Critical Minerals List: Final 2025 List of Critical
Minerals | US Department of the Interior
Traxys is a leading global commodity trader and supply chain manager and has been appointed under the US
Government’s Project Vault initiative to support critical minerals procurement in the US.
ASX:ADN | andromet.com.au Andromeda Metals Ltd | IMARC Conference 2026 11
Potential to become a leading global producer of low-cost, low-carbon HPA
HPA Scoping Study Results
AUD USD
Target Production (annual) 10,000 tpa
NPV10 (pre-tax) $1,480 million US$947 million
NPV10 (post-tax)1 $1,010 million US$647 million
IRR2 88% (pre-tax) 69% (post-tax)
Revenue $6,403 million US$4,098 million
HPA Product Sale Price3 $31,250 / t US$20,000 / t
Cash Operating Cost4 $4,718 / t US$3,020 / t
Cash Operating Margin (%) 85%
Average Annual EBITDA $247 million US$158 million
Pre-production Capital Cost5 $155 million US$99 million
Project Life6 24 years
Notes (1) Refer to ADN ASX dated 18 Sept 2025 titled Results of HPA Scoping Study ; all material assumptions and technical parameters underpinning the estimates and forecast financial information continue to apply and have not materially changed. (2) Assumes company tax rate of
30% (3) Based on HPA market analysis, which may not reflect actual offtake agreements entered into. (4) Excludes potential sales of silicate by-products. (5) Includes ~30% contingency, excludes additional costs for PFS, marketing and other studies including ongoing test work estimated
to take approximately 2 years (subject to available funding) and cost approximately $4 million. (6) Nominal Project Life of 24 years modelled, including approximately 2 years of design and construction for an HPA Production Facility with a 22-year production life. (7) High Purity Alumina
Special Report, CRU, October 2025. (8) High Purity Alumina Market Assessment, FutureBridge (commissioned by Andromeda), August 2025. (9) Pre-production capital cost per tonne of annual production capacity.
Market-Leading Economics7,8
9
ASX:ADN | andromet.com.au Andromeda Metals Ltd | IMARC Conference 2026 12
Investment Highlights
Development-ready
industrial minerals
project
Expansion into
high-value
critical minerals
markets
Notes (1) Refer to ADN ASX dated 15 April 2026 titled Great White Project Early Works Update. (2) Refer to ADN ASX dated 19 August 2026 titled Andromeda Signs Strategic HPA Supply HOA with Traxys.
The HOA is non-binding and there is no guarantee a definitive sales agency agreement will be entered into. Indicative sales value based on the pricing adopted in the 2025 HPA Scoping Study. (3) Refer
to ADN ASX dated 18 Sept 2025 titled Results of HPA Scoping Study; all material assumptions and technical parameters underpinning the estimates and forecast financial information continue to apply
and have not materially changed. (4) Refer to ADN ASX dated 24 August 2026 titled Andromeda Achieves 4N HPA at Continuous Pilot Scale. (5) Refer to ADN ASX dated 29 October 2026 titled
Andromeda Produces 4N+ HPA to 99.9989% Purity and Send Inaugural Sample to Japan for Customer Evaluation
HPA Project
De-risked and construction-ready: Early Works complete — access road,
bulk earthworks, grade control and geotechnical drilling completed, and key
long-lead equipment fabricated and stored in Australia
Strong project economics: A$763m post-tax NPV and 43% IRR across staged
development over 3-stages with 28-year mine life
✓
Revenue visibility: Stage 1A+ production underpinned by binding offtake
agreements
✓
Development Pathway: Credit-approved $A75 million debt facility with
Merricks Capital, continuing to pursue funding, corporate and strategic
opportunities to unlock value from the development-ready Great White
Project 1
➜
US market access: Non-binding HOA with Traxys North America for a
potential five-year sales agency targeting 2,000tpa of HPA into the US
✓
Strong project economics: Scoping Study3 shows market-leading economics
globally for capital intensity and cost of production
✓
Technical derisking: Multiple samples of 4N+ HPA produced to 99.9989%
purity from Great White kaolin at continuous pilot scale4,5
✓
Customer evaluation program commenced: Inaugural 4N+ sample sent to
Japan for customer evaluation by high-tech manufacturer5
The Great White Project
Dual-sector positioning across industrial and critical minerals
Planning Pre-feasibility study: Engineering, design and operating data being
generated to support the next phase of technical studies; amorphous silica
co-product opportunities under evaluation
➜
✓
Andromeda
The Great White
Mineral Company
For more information about the Company, please
visit our website, www.andromet.com.au or contact:
Investor Relations
1800 161 380 (within Australia)
+61 8 7089 9819 (from outside Australia)
ir@andromet.com.au
ASX:ADN | andromet.com.au
ASX:ADN | andromet.com.au Andromeda Metals Ltd | IMARC Conference 2026 14
APPENDIX
ASX:ADN | andromet.com.au Andromeda Metals Ltd | IMARC Conference 2026 15
High-quality kaolin products for premium ceramics
Premium Quality Positioning in the Global Kaolin Market
Notes (1) FeTi index: (% Fe2O3 + TiO2) / % Al2O3 x 1000; Source: Galesk Consultancy SLU, from proprietary database compiled from public data.
(2) As determined by testing conducted on Great White CRM by Instituto de Tecnología Cerámica (ITC), located at the University of Castellón in Spain, and IberoClays.
Low Iron/Alumina ratio
(Fe2O3/Al2O3) vs global kaolin samples
High dry mechanical strength is highly valued in large format porcelain tiles
High whiteness is retained which is valued in high-quality porcelainware and ceramic tiles
IDEAL FOR WHITE AND SUPER-
WHITE PORCELAIN TILES
GREAT WHITE CRM T
A refined, high-quality ceramic
product for the high-end
ceramic tile and porcelain slab
market
Alumina min. 36.5%
Iron max. 0.55%
Whiteness
min. ISO B
83%
IDEAL FOR PREMIUM
CERAMIC BODIES
GREAT WHITE KCM 90
A semi-refined, high-quality
kaolin for direct use, further
refinement, or upgrading of
inferior kaolins
Alumina min. 35%
Iron max. 0.7%
IDEAL FOR PORCELAIN SLABS
AND TABLEWARE
GREAT WHITE CRM P
A refined, high-quality ceramic
product for the high-end porcelain
tableware market
Alumina min. 35%
Iron max. 0.6%
Whiteness /
translucency
min. ISO B
82%
ASX:ADN | andromet.com.au
ASX:ADN | andromet.com.au Andromeda Metals Ltd | IMARC Conference 2026 16
High Purity Alumina (HPA)
What is HPA used for?
Light-emitting diodes (LEDs) Lithium-ion battery (LIB) separators
HPA underpins the global transition to low-carbon and energy efficient technologies
LEDs
50%
LIB separators
40%
Other
semiconductors
2%
Phosphor
applications
2%
Sapphire
glass
3%
Polishing & CMP
slurries
3%
Notes (1) High Purity Alumina Special Report, CRU, October 2025
Electronics and Semi-conductors Synthetic sapphire glass
High Growth End-Use Markets1
Competing 3N-5N HPA Demand by End Use1
ASX:ADN | andromet.com.au
ASX:ADN | andromet.com.au Andromeda Metals Ltd | IMARC Conference 2026 17
Next Generation HPA applications
HPA is used in next generation applications, including data centres powering AI, aerospace and defence1
Synthetic Sapphire for
Defence Electronics
Semi-conductors and Military
Electronics
Armored Vehicles and
Soldier Protection
Semi-conductors powering AI
Optical and
Surveillance Technology
Aerospace
Defence
Notes (1) High Purity Alumina Market Assessment, FutureBridge (commissioned by Andromeda), August 2025
Defence Aerospace and
Turbine Components
ASX:ADN | andromet.com.au
Share your feedback
Discover