Quarterly Activity Report – December 2025
Andromeda Metals Limited (ASX: ADN) (Andromeda, the Company) reports the following activities during
the quarter ended 31 December 2025, demonstrating continued progress in advancing both the Great
White Project (GWP) and high purity alumina (HPA) Project.
HIGHLIGHTS
GREAT
WHITE
PROJECT
• Cornerstone equity process – Due diligence and discussions on terms and
documentation were progressed with a cornerstone investor for an asset level
investment in both the GWP and the HPA Project.1
• Debt funding process – Fulfilment of conditions precedent and finalisation of binding
documentation were progressed, for the credit approved $75 million debt facility with
Merricks Capital.2
• Capital Raising – Successful raising of over $14 million (before costs) in capital to
support commencement of Early Works and to progress the HPA Project.
• Early Works – Commencement of activities following satisfaction of $4.5 million in
environment compliance obligations.3
HPA
PROJECT
• Next stage of commercialisation commenced, with Great White sample preparation
and initial test work underway on feedstock to be used in pilot scale test work.
• Engineering design of the pilot scale continuous HPA production process was refined,
along with selection of metallurgical components required for the test work.
Sarah Clarke, Andromeda’s Acting Chief Executive Officer said:
“Andromeda is pleased with the meaningful progress achieved this quarter, having reached significant
milestones across both our key projects – the Great White Project and HPA Project.
“Early Works activities for the Stage 1A+ development at the Great White Project are well underway,
following lodgement of the rehabilitation bond and payment of required environmental compliance
obligations.
“Our HPA Project is also advancing, with the purification, preparation and testing of the Great White
kaolin feedstock along with the detailed design and selection of components required for the pilot scale
test work.
“These strategic activities were made possible through a successful capital raising which secured more
than $14 million in funds from institutional investors and existing shareholders.
“It’s exciting to be on the ground and starting the foundational activities that will position us for the
development of the Great White Project, as we continue to advance the funding process to support a
final investment decision.”
1
Conclusion of this process subject to due diligence, relevant approvals, agreement on terms, and finalisation of documentation.
2
Final approvals and execution of an agreement remain subject to finalisation of the balance of funding.
3
Includes lodgement of a $3.79 million rehabilitation bond and payment of $670,000 to the Native Vegetation Fund to satisfy
the Significant Environmental Benefit (SEB) obligations were required.
Andromeda Metals Limited ASX: ADN
ASX Announcement
10/431 King William Street
Adelaide, SA 5000
Tel:+61 8 7089 9800
ir@andromet.com.au
30 January 2026
ABN
75 061 503 375
Andromeda Metals Limited | 2
Discussion
Andromeda reports the following activities, undertaken during the quarter ended 31 December 2025.
GREAT WHITE PROJECT (GWP)
The Company continued progressing its project funding process to support a final investment decision
(FID) for the Stage 1A+ development of the GWP, while also undertaking a capital raising which enabled
the commencement of Early Works activities.
Project funding
During the quarter, due diligence processes and discussions on terms and documentation were
progressed with a cornerstone equity investor, for an investment at the asset level for both the GWP and
the HPA Project. The conclusion of this process is subject to due diligence, relevant approvals, agreement
on terms, and finalisation of documentation.
The Company also progressed the fulfilment of conditions precedent and finalisation of binding
documentation for the credit approved $75 million debt facility with Merricks Capital. Final approvals
and execution of an agreement remain subject to finalisation of the balance of funding for Stage 1A+.
Capital Raising
To support the continued advancement of the GWP, the Company raised over $14 million before costs
in capital (Capital Raising), via:
• Share Placement – successful placement of new fully paid ordinary shares (New Shares) which
raised $13 million, with significant demand from institutional and sophisticated investors4;
• Share Purchase Plan (SPP) – to eligible shareholders on the same terms as the Share Placement,
which raised $996,000 before costs5; and
• $30,000 participation by a Director who was not a shareholder at the time of the Capital Raising,
with the securities issued following shareholder approval obtained at a General Meeting held on
10 December 2025.
The price under the Capital Raising offers was $0.0175 per New Share, representing a discount of:
• 16.7% to the closing price of $0.021 on Wednesday, 15 October 2025 (being the trading day prior
to the announcement of the Capital Raising); and
• 9.8% to the 15-trading day volume weighted average price of $0.0194, calculated up to and
including Wednesday, 15 October 2025.
The funds raised under the Capital Raising are being used to:
• Support the development of the GWP, including:
o Early Works activities
o Stage 1A+ equipment procurement
• Advancement of the HPA Project
• Product marketing – across both GWP and the HPA Project, and,
• General working capital and costs of the Capital Raising.
Participants under both the Share Placement and SPP also received three (3) free attaching options for
every five (5) New Shares allocated (New Options) exercisable at $0.026 for a fully paid ordinary share,
expiring 2 years from the date of issue.
Following the issuing of a prospectus and approval by shareholders at a General Meeting of the
Company, 493,582,967 options were issued and listed on ASX under the ticker ADNOD. Each New Option
will expire on 11 December 2027 and, if exercised, will provide an additional $12.8 million in capital for the
Company.
4
Refer to ADN ASX dated 17 October 2025 titled Successful completion of $13 million Placement.
5
Refer to ADN ASX dated 18 November 2025 titled Results of Share Purchase Plan.
Andromeda Metals Limited | 3
Operations
During the quarter, in addition to supporting ongoing Project Funding due diligence processes, across
both the debt and cornerstone equity funding processes, Early Works activities were commenced at GWP
supported by funds raised under the Capital Raising.
Prior to the commencement of Early Works activities, lodgement of a $3.79 million rehabilitation bond and
payment of $670,000 to the Native Vegetation Fund to satisfy the Significant Environmental Benefit (SEB)
obligations were required. The rehabilitation bond is required as part of the South Australian Department
for Energy and Mining’s (DEM) Rehabilitation Financial Assurance, with the SEB payment required as part
of the Company’s compliance with its approved Program for Environment Protection and Rehabilitation
(PEPR).
Following satisfaction of these precedent environment compliance obligations during the quarter,
Andromeda was able to commence Works at the GWP.
Site preparation activities were undertaken, including establishment of the mine access, installation of
mine site entrance gate and signage, erection of fencing and geotechnical drilling.
Activities undertaken subsequent to the quarter, include:
• Commencement of bulk earthworks for the Stage 1A+ processing plant;
• Continued erection of fencing on the Mining Lease;
• Commencement of grade control drilling; and,
• Engineering Detailed Design for the Stage 1A+ processing plant and supporting water
infrastructure.
A summary of planned pre-construction Early Works activities, with their progress status, include:
• Payment of environmental compliance payments ✓Completed
• Site preparation activities, including:
– Establishment of mine access
– Bulk earthworks for the Stage 1A+ processing plant
✓Completed
Underway
• Geotechnical Drilling ✓Completed
• Grade Control Drilling Underway
• Insurance arrangements ✓Completed
• Finalisation of the Engineering Detailed Design for:
– Stage 1A+ processing plant
– Supporting water infrastructure
Underway
Underway
• Transport of key long-lead equipment items, currently
fabricated and warehoused overseas, to Australia
Underway
Andromeda Metals Limited | 4
Following are images showing the state of Early Works activities undertaken to date.
Site entrance and signage
Establishment of mine access
Bulk earthworks for the Stage 1A+ Processing Plant
Andromeda Metals Limited | 5
Erection of fencing on Mining Lease
During the quarter, procurement of long lead items for Stage 1A+ was also progressed.
In anticipation of a final investment decision and supported by the funds raised in the recent Capital
Raising, preparations were made during the quarter for the transport of key long-lead equipment items,
which are currently fabricated and warehoused overseas, to Australia.
The current status of long-lead equipment items is as follows:
• Fluid bed dryer – factory acceptance testing (FAT) completed, warehoused, ready for shipment;
• Thickener – FAT completed, warehoused, preparations underway for shipment to Australia;
• Drum washer – FAT completed, warehoused, ready for shipment;
• Filter Press – FAT completed, warehoused, preparations underway for shipment to Australia; and,
• Filter Cake Feeder – engineering design complete, with fabrication to commence following an
anticipated final investment decision.
Filterpress – fabricated and being prerpared for shipment
Thickener – fabricated and being prerpared for shipment
Andromeda Metals Limited | 6
The Company also prepared for the procurement of the ‘balance of plant’ capital and infrastructure items
for Stage 1A+. Due to anticipated demand and purchasing lead times, subsequent to the quarter a
deposit will be paid for the microturbines required to power the Stage 1A+ processing plant and GWP
mine site, which is intended to be secured through a lease-to-own arrangement.
During the quarter, the Company produced a 3D virtual walk-through of the updated design and layout
of the Stage 1A+ Processing Plant, which can be viewed by clicking on the image below:
Operations at the Streaky Bay Pilot Plant were managed to support provision of samples, advancement
of the Stage 1A+ detailed plant design and engineering, and for the supply of the feedstock for pilot
scale test work for the continuous production of commercial samples of HPA.
During the quarter there were no lost time injuries, and no reportable environmental incidents.
TECHNICAL
During the quarter, the program of testing samples of Great White HRM™ in overseas markets to assess its
suitability across a range of potential customer applications, was progressed. This included a testing
program across a range of potential customer applications in Japan, Singapore and other Asian markets.
HIGH PURITY ALUMINA (HPA) PROJECT
Following completion of the Scoping Study demonstrating market-leading economics of producing HPA
from high-quality Great White kaolin using Andromeda’s innovative process6, Andromeda is progressing
the HPA opportunity with pilot scale test work. The aim is to produce commercial samples of the critical
mineral HPA for distribution to potential customers for evaluation.
During the quarter, Andromeda progressed the HPA Project with the production of a refined Great White
kaolin feedstock for use in the pilot scale test work, the commencement of initial testing of that feedstock,
and the design and procurement of metallurgical components required for the pilot scale test work.
6 Refer ADN ASX dated 18 September 2025 titled HPA Scoping Study demonstrates market-leading economics of Andromeda’s innovative
technology. All material assumptions and technical parameters underpinning the estimates and forecast financial information continue to
apply and have not materially changed.
Andromeda Metals Limited | 7
Potential customers require the HPA samples to be produced through a continuous process. Hence,
through replicating the successful test work undertaken to date, the pilot scale test work is expected to
produce 4N HPA (99.99% purity) using a continuous process, rather than the batch processing used
previously. This will also support the engineering and design of a full-scale production plant for future
studies.
The high-quality Great White kaolin was sent and processed for use as feedstock, with initial batch lab-
scale tests conducted to determine the initial grade and leachability, as seen in the following images:
Primary leachate 1-stage purification 2-stage purification
In parallel, the engineering design of the continuous HPA production process to be used for the test work
was refined, with the selection of various components progressed, including the following items:
Purification columns Leaching unit Storage tank
Andromeda’s innovative process can produce HPA in a wide range of product forms, from amorphous
to crystalline (gamma to alpha), and is flexible to produce HPA to suit individual customer and application
needs. The samples of the 4N HPA produced from the pilot scale test work will be used for evaluation by
prospective customers to assist in determining and designing the required end product form.
In addition to the HPA samples, the pilot scale test work will produce a silica by-product. Further analysis
and assessment of the by-product is planned as part of this pilot scale test work.
Andromeda Metals Limited | 8
South Australia Premier’s Awards 2025
Andromeda was pleased that it’s HPA Project was nominated in the 2025 Premier’s Awards for the Energy
and Mining industry, and subsequently, named as a Finalist in the Productivity improvement – Resources
category.
During the quarter, the Company attended the awards ceremony, although was not ultimately
successful. Andromeda congratulates the joint winners in our category, BHP and Wilco Technologies.
REGIONAL EXPLORATION
Eyre Kaolin Project
(Andromeda has earned a 51% interest by expending $750,000 by November 2024)
The Eyre Kaolin Joint Venture (EKJV) comprises four tenements located in close proximity to the GWP,
which include kaolin prospects with complementary properties to those at GWP.
During the quarter, the Company awaited the final analytical results, from an external provider, for the
samples collected during drilling conducted previous at the Chairlift Deposit. The drilling was undertaken
to test for potential extensions and better define areas of the deposit that best complement Great White
kaolin, with high brightness and low titanium.
Additionally, Andromeda continued to progress the assessment of approximately 300 historic drillholes
within the EKJV Project and surrounding area. Most of these holes were previously assayed only for
uranium or heavy mineral sands, are now being reanalysed for a broader spectrum of commodities. This
analysis was postponed due to the priorities of participating in due diligence as part of the project funding
process, and the planning and execution of Early Works activities at the GWP.
The Company has the right to earn a further 29% interest in the EKJV (for a total of 80%) by expending a
further $2 million on exploration by November 2027.
METALS PROJECTS
Andromeda’s strategic focus remains on developing our portfolio of kaolin projects which has resulted in
the Company divesting its gold and copper assets.
During the quarter, the Company continued to await the outcome of the tenement transfer applications
related to the completed sales of the Wudinna Gold Project and Moonta Copper Gold Project, via South
Australia’s subdivision process.
Andromeda Metals Limited | 9
CORPORATE
During the period, the following activities to support greater investor awareness of the Company and its
products, were undertaken:
• Presentation and attendance at the Noosa Mining Conference, at which Sarah Clarke, Acting
CEO, presented an overview of the Company7; and,
• East Coast Research, a third-party research house, published an updated report on Andromeda,
which included information related to the results the HPA Scoping Study, with an updated
valuation. Investors can access all research reports published on the Company’s website under
Investors > Broker Reports: www.andromet.com.au/investors/broker-reports-disclaimer/
Finance
Cash and cash equivalents at the end of the quarter were $10,062k, an increase of $5,715k from the
previous quarter's closing balance of $4,347k. The increase is primarily a result of the Capital Raising which
raised approximately $14 million before costs (refer to earlier Project Funding section) and expenditure
incurred in relation to the commencement of Early Works at GWP (refer to earlier Operations section).
The Company continued initiatives to minimise expenditure and conserve cash. Such measures include:
• Mick Wilkes electing not to receive any director fees until the Project is fully financed;
• Sue-Ann Higgins accepting reduced fees than what she would ordinarily have received as an
Executive Chair;
• Continuation of a strategy allowing directors to have some or all of their remuneration or fees
satisfied by the issue of zero exercise price options (ZEPOs) for the period from 1 January 2026 to
the earlier of final investment decision and 30 June 2026, using the 10-trading day VWAP of
Andromeda shares up to and including 31 December 2025, being $0.01343 (subject to shareholder
approval, with those fees to be paid in cash if shareholder approval is not obtained).
During the quarter, net funds used in operating activities were $1,176k and net funds used in investing
activities were $6,076k. Net funds received from financing activities were $12,967k.
Exploration and Evaluation Expenditure during the quarter was $1,870k. Full details of exploration and
evaluation activity during the Quarter are set out in this report.
There were no substantive mining production and development activities during the quarter.
Payments to related parties of the Company and their associates during the quarter were $94k, consisting
of executive director salaries and payments to Galesk Consultancy.
Capital Structure
During the period, the following changes in securities in the Company occurred:
• 24 October – 742,857,143 Ordinary shares were issued in relation to the Capital Raising via a
successful Share Placement which raised $13 million before costs.
• 21 November:
o 56,914,350 Ordinary shares were issued in relation to the Capital Raising via a Share
Purchase Plan which raised $996,000 before costs.
o 9,266,360 Unlisted ZEPOs were issued in lieu of director fees for the period from
appointment to 31 December 2025, following shareholder approval.
7 Refer to ADN ASX dated 14 November 2025 titled Noosa Mining Conference Presentation.
Andromeda Metals Limited | 10
• 11 December:
o 492,554,396 Listed options were issued (ASX: ADNOD) in relation to the Capital Raising, via
a Share Placement and a Share Purchase Plan, and under a Prospectus.
o 1,714,285 Ordinary shares and 1,028,571 Listed options were issued through Director
participation in the Capital Raising, following Shareholder approval.
o 5,272,109 Ordinary shares were issued following the conversion of an equivalent number
of ZEPOs under an employee incentive scheme, in lieu of remuneration.
• 31 December – 1,650,000 Unlisted options lapsed following their expiry, without exercise or
conversion.
• 16 January - 128,571 Ordinary shares were issued following the conversion of an equivalent
number of listed options.
This announcement has been approved for release by the Board of Directors of Andromeda Metals Limited.
For more information about the Company and its projects, please visit our website, or contact:
Manager, Investor Relations & Corporate Affairs
Patrick Sinclair
T: 08 7089 9819
M: 0403 708 431
E: Patrick.Sinclair@andromet.com.au
FORWARD-LOOKING STATEMENTS
This document contains or may contain certain forward-looking statements and comments about future events, that
are based on Andromeda's beliefs, assumptions and expectations and on information currently available to
management as at the date of this document. Often, but not always, forward-looking statements can generally be
identified by the use of forward-looking words such as "may", "will", "expect", "plan", "believes", "estimate", "anticipate",
"outlook", and "guidance", or similar expressions. Such statements are only expectations or beliefs and are subject to
inherent risks and uncertainties which could cause actual values, results or performance achievements to differ
materially from those expressed or implied in this presentation. Where Andromeda expresses or implies an
expectation or belief as to future events or results, such expectation or belief is expressed in good faith and on a
reasonable basis. No representation or warranty, express or implied, is made by Andromeda that the matters stated
in this presentation will in fact be achieved or prove to be correct. Except as required by law, Andromeda undertakes
no obligation to provide any additional or updated information or update any forward-looking statements, whether
on a result of new information, future events, results or otherwise. Readers are cautioned against placing undue
reliance on forward-looking statements. These forward-looking statements are not guarantees of future performance
and involve known and unknown risks, uncertainties, assumptions and other important factors, many of which are
beyond the control of Andromeda, the directors, and management of Andromeda.
Andromeda Metals Limited | 11
SUMMARY SCHEDULE OF TENEMENTS AS AT 31 DECEMBER 2025
Project Tenement Tenement Name Area
km2
Registered Holder or Applicant
Nature of
Company's
Interest %
South Australia
The Great White
Project
ML 6532 Great White 319 ha Andromeda Industrial Minerals Pty Ltd1 AIM 100%
MPL 163 Water Pipeline MPL 78 ha Andromeda Industrial Minerals Pty Ltd AIM 100%
MPL 164 Access Road MPL 13 ha Andromeda Industrial Minerals Pty Ltd AIM 100%
EL 6588 Tootla 372 Andromeda Industrial Minerals Pty Ltd2
AIM 100%
EL 6202 Mt Hall 147 Andromeda Industrial Minerals Pty Ltd
AIM 100%
EL 6426 Mt Cooper 648 Andromeda Industrial Minerals Pty Ltd
AIM 100%
Eyre Kaolin
Project3
EL 6663 Aspen 976 Peninsula Exploration Pty Ltd EK 51%
Peninsula 49%
EL 6664 Whistler 452 Peninsula Exploration Pty Ltd EK 51%
Peninsula 49%
EL 6665 Hotham 875 Peninsula Exploration Pty Ltd EK 51%
Peninsula 49%
EL 6666 Thredbo 496 Peninsula Exploration Pty Ltd EK 51%
Peninsula 49%
Mt Hope Kaolin
Project
EL 6286 Mt Hope 227 Andromeda Industrial Minerals NZPty Ltd4 100%
Wudinna Gold
Joint Venture6
EL 6317 Pinkawillinie 156 Peninsula Resources Pty Ltd5 PRL 0%
LAM 100%
EL 6131 Corrobinnie 1,303 Peninsula Resources Pty Ltd PRL 0%
LAM 100%
EL 6489 Wudinna Hill 42 Peninsula Resources Pty Ltd PRL 0%
LAM 100%
EL 5953 Minnipa 184 Peninsula Resources Pty Ltd PRL 0%
LAM 100%
EL 6001 Waddikee Rocks 147 Peninsula Resources Pty Ltd PRL 0%
LAM 100%
Moonta Copper
Gold Project
EL 5984 Moonta-Wallaroo 713 Peninsula Resources Pty Ltd 100% ECR7
EL 5984 Moonta-Porphyry JV 106 Peninsula Resources Pty Ltd 90% ECR
10% AIC Mines Ltd
1 Andromeda Industrial Minerals Pty Ltd (AIM), (incorporated 9 August 2018) is a wholly owned subsidiary of Andromeda Metals Ltd.
2 On 26 July 2024, the 25% share held by GSK (Great Southern Kaolin Pty Ltd (GSK) is a wholly owned subsidiary of Andromeda Metals Ltd.) was transferred to AIM,
resulting in AIM’s interest increasing to 100%.
3 On 15 July 2024, Eyre Kaolin Pty Ltd (EK) (a wholly owned subsidiary of Andromeda Metals Ltd) earned the right to claim a 51% interest in the Eyre Kaolin Project
under a farm in agreement with Peninsula Exploration Pty Ltd (Peninsula). Under the agreement Eyre Kaolin Pty Ltd can earn a further 29% (for a total of 80%).
4 Andromeda Industrial Minerals NZ Pty Ltd is a wholly owned subsidiary of Andromeda Industrial Minerals Holdings Pty Ltd.
5 Peninsula Resources Pty Ltd (PRL), (incorporated 18 May 2007) is a wholly owned subsidiary of Andromeda Metals Ltd.
6 PRL remains the registered holder of these tenements whilst a subdivision or transfer is being effected – if subdivided PRL will retain some of the area of these
tenements, refer to ADN ASX announcement dated 23 April 2024 title Completion of Sale of Interest in Wudinna Gold Project.
7 PRL remains the registered holder of EL 5984 whilst the subdivision or transfer of this tenement is being effected – if subdivided PRL will retain some of the area of
this tenement – refer to ADN ASX announcement dated 24 January 2024 titled Completion of Sale of Moonta Copper Gold Project.
Rule 5.5
Current quarter Year to date
$A’000 (6 months)
$A’000
1
1.1 - -
1.2
- -
- -
- -
(476) (971)
(760) (1,674)
1.3 - -
1.4 62 96
1.5 (2) (5)
1.6 - -
1.7 - -
1.8 - -
1.9 (1,176) (2,554)
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
ANDROMEDA METALS LIMITED
ABN Quarter ended (“current quarter”)
(a) exploration & evaluation
(b) development
(c) production
(d) staff costs
(e) administration, corporate, marketing and R&D costs
Dividends received (see note 3)
75 061 503 375 31 December 2025
Consolidated statement of cash flows
Cash flows from operating activities
Receipts from customers
Payments for
Interest received
Interest and other costs of finance paid
Income taxes paid
Government grants and tax incentives
Other (provide details if material)
Net cash from / (used in) operating activities
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms. Page 1
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
Current quarter Year to date
$A’000 (6 months)
$A’000
2
2.1
- -
- -
(416) (553)
(1,870) (3,068)
- -
(3,790) (3,790)
2.2
- -
- -
- -
- -
- -
2.3 - -
2.4 - -
2.5
- -
2.6 (6,076) (7,411)
3
3.1 14,026 14,026
3.2 - -
3.3 - -
3.4 (1,009) (1,036)
3.5 - -
3.6 - -
3.7 - -
3.8 - -
3.9 (50) (105)
3.10 12,967 12,885
Consolidated statement of cash flows
Cash flows from investing activities
Payments to acquire or for:
(a) entities
(b) tenements
(b) tenements
(c) property, plant and equipment
(d) investments
(e) other non-current assets
Cash flows from loans to other entities
Dividends received (see note 3)
(c) property, plant and equipment
(d) exploration & evaluation (capitalised)
(e) investments
(f) other non-current assets
Proceeds from the disposal of:
(a) entities
Net cash from / (used in) investing activities
Cash flows from financing activities
Proceeds from issues of equity securities (excluding
convertible debt securities)
Proceeds from issue of convertible debt securities
Proceeds from exercise of options
Other
- Government grants, subsidies and tax incentives
Net cash from / (used in) financing activities
Transaction costs related to issues of equity securities or
convertible debt securities
Proceeds from borrowings
Repayment of borrowings
Transaction costs related to loans and borrowings
Dividends paid
Other (Lease repayments)
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms. Page 2
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
Current quarter Year to date
$A’000 (6 months)
$A’000
4
4.1
4,347 7,142
4.2
(1,176) (2,554)
4.3
(6,076) (7,411)
4.4
12,967 12,885
4.5
-
-
4.6 10,062 10,062
Current quarter Previous quarter
$A’000 $A’000
5.1 10,062 4,347
5.2 - -
5.3 - -
5.4 - -
5.5 10,062 4,347
Current quarter
$A'000
6.1
(94)
6.2
0
Consolidated statement of cash flows
Net increase / (decrease) in cash and cash
Cash and cash equivalents at beginning of period
Net cash from / (used in) operating activities (item 1.9 above)
Bank balances
Call deposits
Bank overdrafts
Other (provide details)
Cash and cash equivalents at end of quarter (should
equal item 4.6 above)
6 Payments to related parties of the entity and their associates
Net cash from / (used in) investing activities (item 2.6 above)
Net cash from / (used in) financing activities (item 3.10 above)
Effect of movement in exchange rates on cash held
Cash and cash equivalents at end of period
5 Reconciliation of cash and cash equivalents
at the end of the quarter (as shown in the consolidated
statement of cash flows) to the related items in the accounts
Aggregate amount of payments to related parties and their associates included in item 1
Aggregate amount of payments to related parties and their associates included in item 2
Note: if any amounts are shown in items 6.1 or 6.2, your quarterly activity report must include a description of, and an explanation for, such payments.
The amount at items 6.1 and 6.2 comprises executive director salaries, bonuses & termination payments, non-executive director fees and consulting fees
paid to directors or related corporations of directors of the Company during the quarter.
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms. Page 3
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
Total facility Amount drawn at
amount at quarter end quarter end
$A’000 $A’000
7.1 - -
7.2 - -
7.3 90 13
7.4 90 13
7.5 77
7.6
8 $A’000
8.1 (1,176)
8.2 (1,870)
8.3 (3,046)
8.4 10,062
8.5 77
8.6 10,139
8.7 3.33
8.8
believe that they will be successful?
Loan facilities
Credit standby arrangements
Other (credit card facility)
Total financing facilities
Unused financing facilities available at quarter end
7 Financing facilities
Note: the term “facility’ includes all forms of financing arrangements available
to the entity.
Add notes as necessary for an understanding of the sources of finance
available to the entity.
Cash and cash equivalents at quarter end (item 4.6)
Unused finance facilities available at quarter end (item 7.5)
Total availa