High Purity Alumina Project Update
Released
Released
Announcement PDF
Sign-up and log into ADN’s Investor Hub
High Purity Alumina Project Update
Key Highlights:
• Commissioning underway at Andromeda’s HPA pilot plant, with testwork to run through
Q3 2026
• Commercial 4N HPA samples targeted in H2 2026 for customer qualification
• Builds on 99.9985% HPA purity achieved at laboratory scale
• 2025 Scoping Study confirmed strong economics and low-cost production potential
• Potential upside from by-products including silica and gallium
• Supports Andromeda’s broader HPA commercialisation strategy
Andromeda Metals Limited (ASX: ADN) (Andromeda, the Company) is pleased to provide an
update on its High Purity Alumina (HPA) project, aimed to commercialise the critical mineral
production using high-quality Great White kaolin as feedstock in its proprietary process (HPA
Project).
The HPA Project pilot plant1 has now been assembled, with commissioning underway and pilot
testwork expected to continue through Q3 2026. This marks a key milestone in Andromeda’s
transition toward continuous process production of HPA and the planned generation of
commercial samples for customer qualification in H2 2026.
Andromeda is advancing a next-generation HPA supply chain, independent of traditional
aluminium markets, leveraging its high-quality, low-impurity Great White kaolin as feedstock and
innovative processing pathway. The pilot plant project is the first step in scaling the Company’s
proprietary processing technology, which has already demonstrated HPA purity of 99.9985% at
laboratory scale.
The value adding potential, of this HPA opportunity, was highlighted in the Company’s 2025 Scoping
Study2, which showed strong project economics and the potential for Andromeda to be highly
competitive globally, particularly on cost of production and capital intensity.
With pilot plant commissioning now underway, Andromeda has entered the next phase of its HPA
commercialisation strategy, progressing toward customer qualification, future feasibility studies and
broader market entry initiatives.
1
Refer ADN ASX dated 7 October 2025 titled HPA Project – Next phase of commercialisation underway.
2
Refer ADN ASX dated 18 September 2025 titled HPA Scoping Study demonstrates market-leading economics of Andromeda’s
innovative technology; all material assumptions and technical parameters underpinning the estimates and forecast financial
information continue to apply and have not materially changed.
Andromeda Metals Limited ASX: ADN
ASX Announcement
10/431 King William Street
Adelaide, SA 5000
Tel:+61 8 7089 9800
ir@andromet.com.au
22 June 2026
ABN
75 061 503 375
Andromeda Metals Limited | 2
HPA Pilot Plant Progress Update
Commissioning of the HPA pilot plant follows the successful design, manufacture, delivery and
construction of key metallurgical components, together with the production and initial processing
of refined Great White kaolin feedstock to be used in the testwork.
The HPA pilot testwork program is expected to:
• Produce HPA using a continuous process, transitioning from the batch processing used at
laboratory scale;
• Generate commercial samples of 4N HPA for evaluation by potential customers; and
• Prove scalability of the proprietary process to support engineering design of a commercial
facility for future feasibility studies.
Analysis of by-products
As advised in the Scoping Study, in addition to commercial samples of 4N HPA, the pilot plant
testwork will also generate by-product materials for further analysis and assessment of potential
value.
Importantly, the 2025 HPA Scoping Study did not incorporate any potential revenue from the sale
of by-products and instead assumed costs associated with their disposal. The pilot testwork will,
however, generate by-product materials that will be further characterised and assessed for
potential commercial applications. Accordingly, there is potential for these materials to provide an
additional value pathway, subject to the outcomes of ongoing testwork and evaluation.
Amorphous Silica
A key by-product stream produced during testwork is expected to comprise amorphous silica,
which will be characterized and assessed for potential commercial applications. Amorphous silica,
also known as precipitated silica, is widely used in the rubber industry and as a high-value
agricultural fertiliser.
Potential recovery of additional valuable by-products
The efficacy of Andromeda’s proprietary process is underpinned by the exceptional quality of its
kaolin feedstock sourced from the Great White Project (GWP). The XRF assay results of the Great
White kaolin feedstock provided for the HPA testwork (refer to Table 1) demonstrates that the feed
material consistently exhibits high alumina (Al₂O₃) content, accompanied by very low levels of
deleterious elements such as calcium (Ca), potassium (K), magnesium (Mg) and sodium (Na). This
favourable chemical profile of the Great White kaolin feedstock is a key advantage, as it supports
efficient downstream processing and the production of high-purity end products.
Table 1. XRF analyses of kaolin feedstock sourced from the GWP for the HPA testwork
SAMPLE
PP-FS-A
(%)
PP-FS-B
(%) SAMPLE
PP-FS-A
(%)
PP-FS-B
(%)
Al2O3 38.37 38.55 MnO <0.01 <0.01
BaO 0.02 0.02 Na2O 0.01 0.01
CaO 0.04 0.04 P2O5 0.06 0.06
Cr2O3 <0.01 <0.01 SiO2 46.73 46.99
Fe2O3 0.34 0.35 SrO <0.01 0.01
K2O 0.32 0.31 TiO2 0.45 0.46
MgO 0.09 0.1 LOI 13.7 13.69
Andromeda Metals Limited | 3
In addition to the primary alumina content, multi-element assays indicate the presence of gallium
in the Great White kaolin feedstock. (refer to Table 2). Further testwork will assess whether gallium
or other minor elements may be recoverable as part of the Company’s process flowsheet.
Gallium (Ga) is a strategically important metal considered a critical mineral due to its use in
advanced and defence technologies, and severe supply‑chain concentration and geopolitical
vulnerability.
Gallium is used in advanced electronics and semiconductors, such as those used in data
warehouses to support the increasing adoption of artificial intelligence (AI), as well as aerospace
and defence systems.
The refining and primary supply of gallium is extremely concentrated, with China controlling
99 percent of the world’s primary gallium, and its geopolitical vulnerability evidenced by export
controls placed on gallium being imposed by China to the US in July 2023, which escalated in
December 2024 to an outright ban on gallium exports to the United States (later suspended).
Gallium is considered a critical mineral in Australia3, the United States4, the European Union5 as well
as also listed as critical or strategic by Japan, South Korea, the UK and India3, and included as a
Critical Raw Material in NATO defence‑critical materials assessments6, reflecting its importance
across allied technology and defence supply chains.
Table 2. Multi-element analyses of kaolin feedstock sourced from the GWP for the HPA testwork
Element
PP-FS-A
(ppm)
PP-FS-B
(ppm)
PP-FS-A
(ppm)
PP-FS-B
(ppm)
Ba 152.5 152 Sr 53 50
Ce 181 178 Ta 1 1
Cr 15 15 Tb 0.77 0.74
Cs 0.36 0.4 Th 16.7 16.8
Dy 4.51 4.28 U 2.07 2.1
Er 2.07 1.86 V 26 25
Eu 1.27 1.12 W 3 2.9
Ga 34.2 35.9 Y 18.6 17.9
Gd 5.43 5.63 Yb 1.64 1.62
Ge 1.7 1.8 Zr 96 95
Hf 2.84 2.8 As 0.1 0.1
Ho 0.73 0.78 Bi 0.03 0.03
La 94.2 93.1 Hg <0.005 <0.005
Lu 0.21 0.2 In 0.013 0.013
Nb 14.7 14.7 Re 0.001 <0.001
Nd 57 55.4 Sb <0.05 <0.05
Pr 18 17.75 Sc 2.2 2.3
Rb 11.7 13.1 Se 0.2 <0.2
Sm 8.39 9 Te 0.03 0.02
3
Refer to the Australia’s Critical Minerals List: Australia’s Critical Minerals List and Strategic Materials List | Department of
Industry Science and Resources
4
Refer to the United States’ Critical Minerals List: Final 2025 List of Critical Minerals | US Federal Register
5
Refer to the European Union’s Critical Minerals List: European Critical Raw Materials Act | European Commission
6
Refer to the NATO’s List of Critical Raw Materials: NATO releases list of 12 defence-critical raw materials | NATO News
Andromeda Metals Limited | 4
Sn 14.2 5.1 Tl <0.02 <0.02
Tm 0.28 0.26
The ability to potentially recover minor elements such as Gallium represents an additional value
pathway and reinforces the strategic importance of Andromeda’s resource. This dual advantage
of high-purity alumina production combined with by-product recovery potential may further
enhance the overall economics and scalability of the HPA development.
Sarah Clarke, Andromeda’s Acting CEO said:
“This is an exciting period for Andromeda, with the commencement of commissioning of the HPA
pilot plant marking the culmination of several years of focused research and development into
producing HPA from our high-quality kaolin.
“Through this work, we have assessed a range of processing pathways, leading to the development
of our proprietary HPA process, which has the potential to position Andromeda as a globally
competitive, low-cost producer of HPA products, using our low-carbon processing technology.
“The commissioning of the HPA pilot plant supports us leveraging the exceptional quality of our
Great White kaolin to produce commercial samples of HPA for targeted customer engagement,
while advancing our pathway to commercial production.
“Importantly, our proprietary processing technology not only represents an opportunity for the
efficient extraction of HPA, but also for other critical minerals contained within the high-quality
kaolin feedstock sourced from Andromeda’s Great White Project.”
Next Steps
Following commissioning of the pilot plant, Andromeda will progress pilot-scale testwork through Q3
2026, targeting the production of commercial 4N HPA samples in H2 2026 for customer qualification.
The results from the pilot program are expected to support future feasibility studies, further assess
potential by-product value streams, and advance the Company’s broader HPA commercialisation
strategy.
This announcement has been approved for release by the Board of Andromeda Metals Limited.
For more information about the Company and its projects, please visit our website at
www.andromet.com.au or contact:
Manager, Investor Relations & Corporate Affairs
Patrick Sinclair
T: 08 7089 9819
M: 0403 708 431
E: Patrick.Sinclair@andromet.com.au
FORWARD-LOOKING STATEMENTS
This document contains or may contain certain forward-looking statements and comments about future
events, that are based on Andromeda's beliefs, assumptions and expectations and on information currently
available to management as at the date of this document. Often, but not always, forward-looking statements
can generally be identified by the use of forward-looking words such as "may", "will", "expect", "plan", "believes",
"estimate", "anticipate", "outlook", and "guidance", or similar expressions. Such statements are only
expectations or beliefs and are subject to inherent risks and uncertainties which could cause actual values,
results or performance achievements to differ materially from those expressed or implied in this presentation.
Where Andromeda expresses or implies an expectation or belief as to future events or results, such expectation
Andromeda Metals Limited | 5
or belief is expressed in good faith and on a reasonable basis. No representation or warranty, express or
implied, is made by Andromeda that the matters stated in this presentation will in fact be achieved or prove
to be correct. Except as required by law, Andromeda undertakes no obligation to provide any additional or
updated information or update any forward-looking statements, whether on a result of new information, future
events, results or otherwise. Readers are cautioned against placing undue reliance on forward-looking
statements. These forward-looking statements are not guarantees of future performance and involve known
and unknown risks, uncertainties, assumptions and other important factors, many of which are beyond the
control of Andromeda, the directors, and management of Andromeda.
COMPETENT PERSONS STATEMENT
Information in this announcement that relates to the geochemical analysis of Great White kaolin feedstock is
based on information compiled and thoroughly reviewed by Mr Eric Whittaker who is a Member of the
Australasian Institute of Mining and Metallurgy (MAusIMM). Mr Whittaker is the Chief Geologist of Andromeda
Metals Limited and has sufficient experience relevant to the style of mineralisation and the activity which he is
undertaking to qualify as a Competent Person as defined in the 2012 Edition of the Australasian Code for
Reporting of Exploration Results, Mineral Resources and Ore Reserves (the “JORC Code”). Mr Whittaker has 30
years of experience in the mining industry. Mr Whittaker consents to the information in the form and context in
which it appears. Mr Whittaker holds Performance Rights in the Company and is entitled to participate in
Andromeda’s employee incentive plan.
Sign-up and log into ADN’s Investor Hub
JORC Code, 2012 Edition – Table 1 Andromeda HPA – Feedstock for Pilot Plant Trial 2026
Section 1 Sampling Techniques and Data
(Criteria in this section apply to all succeeding sections.)
Criteria JORC Code explanation Commentary
Sampling techniques • Nature and quality of sampling (e.g. cut channels, random chips, or specific
specialised industry standard measurement tools appropriate to the minerals under
investigation, such as down hole gamma sondes, or handheld XRF instruments, etc).
These examples should not be taken as limiting the broad meaning of sampling.
• Include reference to measures taken to ensure sample representivity and the
appropriate calibration of any measurement tools or systems used.
• Aspects of the determination of mineralisation that are Material to the Public
Report.
• In cases where ‘industry standard’ work has been done this would be relatively
simple (e.g. ‘reverse circulation drilling was used to obtain 1 m samples from which
3 kg was pulverised to produce a 30 g charge for fire assay’). In other cases more
explanation may be required, such as where there is coarse gold that has inherent
sampling problems. Unusual commodities or mineralisation types (e.g. submarine
nodules) may warrant disclosure of detailed information.
• The analyses presented were conducted on representative
samples from a ~250 kg batch of Great White CRM™ refined
kaolin, which will serve as the feedstock for the HPA Pilot Plant
Trial.
Drilling techniques • Drill type (e.g. core, reverse circulation, open-hole hammer, rotary air blast, auger,
Bangka, sonic, etc) and details (e.g. core diameter, triple or standard tube, depth of
diamond tails, face-sampling bit or other type, whether core is oriented and if so, by
what method, etc).
• Not applicable - manufactured product
Drill sample recovery • Method of recording and assessing core and chip sample recoveries and results
assessed.
• Measures taken to maximise sample recovery and ensure representative nature of
the samples.
• Whether a relationship exists between sample recovery and grade and whether
sample bias may have occurred due to preferential loss/gain of fine/coarse material.
• Not applicable - manufactured product
Logging • Whether core and chip samples have been geologically and geotechnically logged to
a level of detail to support appropriate Mineral Resource estimation, mining studies
and metallurgical studies.
• Whether logging is qualitative or quantitative in nature. Core (or costean, channel,
etc) photography.
• The total length and percentage of the relevant intersections logged.
• Not applicable - manufactured product
Andromeda Metals Limited | 7
Criteria JORC Code explanation Commentary
Sub-sampling
techniques and sample
preparation
• If core, whether cut or sawn and whether quarter, half or all core taken.
• If non-core, whether riffled, tube sampled, rotary split, etc and whether sampled
wet or dry.
• For all sample types, the nature, quality and appropriateness of the sample
preparation technique.
• Quality control procedures adopted for all sub-sampling stages to maximise
representivity of samples.
• Measures taken to ensure that the sampling is representative of the in situ material
collected, including for instance results for field duplicate/second-half sampling.
• Whether sample sizes are appropriate to the grain size of the material being
sampled.
• The two samples analysed were sourced from separate
sub-batches supplied for the pilot plant trial, to assess
variability within the overall batch.
• The results indicate that a satisfactory level of homogeneity
was achieved across the sub-batches and further
demonstrates that the sample sizes and sampling techniques
applied were appropriate.
Quality of assay data
and laboratory tests
• The nature, quality and appropriateness of the assaying and laboratory procedures
used and whether the technique is considered partial or total.
• For geophysical tools, spectrometers, handheld XRF instruments, etc, the
parameters used in determining the analysis including instrument make and model,
reading times, calibrations factors applied and their derivation, etc.
• Nature of quality control procedures adopted (e.g. standards, blanks, duplicates,
external laboratory checks) and whether acceptable levels of accuracy (i.e. lack of
bias) and precision have been established.
• Samples were submitted to Australian Laboratory Services
(ALS) for analytical methods multi-element analyses by
methods ME-XRF26 and ME-MS81.
• ME‑XRF26 is a whole-rock geochemical assay method used to
determine major element composition. The technique
involves lithium borate fusion of the sample to produce a
homogeneous glass disc, which is then directly analysed by
X‑ray fluorescence (XRF).
• ALS ME-MS81 is a multi-element trace analysis technique
based on lithium borate fusion followed by Inductively
Coupled Plasma Mass Spectrometry (ICP-MS). The sample is
fused at high temperature with a lithium borate flux to
achieve complete decomposition of all minerals, including
refractory phases, before the melt is dissolved and analysed.
Full fusion enables determination of total concentrations of
trace and minor elements, including rare earth elements
(REEs), and other trace metals.
• Internal laboratory checks were within acceptable variability
Verification of
sampling and assaying
• The verification of significant intersections by either independent or alternative
company personnel.
• The use of twinned holes.
• Documentation of primary data, data entry procedures, data verification, data
storage (physical and electronic) protocols.
• Discuss any adjustment to assay data.
• Data was checked by alternate company personnel.
Location of data points • Accuracy and quality of surveys used to locate drill holes (collar and down-hole
surveys), trenches, mine workings and other locations used in Mineral Resource
estimation.
• Not applicable - manufactured sample
Andromeda Metals Limited | 8
Criteria JORC Code explanation Commentary
• Specification of the grid system used.
• Quality and adequacy of topographic control.
Data spacing and
distribution
• Data spacing for reporting of Exploration Results.
• Whether the data spacing and distribution is sufficient to establish the degree of
geological and grade continuity appropriate for the Mineral Resource and Ore
Reserve estimation procedure(s) and classifications applied.
• Whether sample compositing has been applied.
• Not applicable - manufactured sample
Orientation of data in
relation to geological
structure
• Whether the orientation of sampling achieves unbiased sampling of possible
structures and the extent to which this is known, considering the deposit type.
• If the relationship between the drilling orientation and the orientation of key
mineralised structures is considered to have introduced a sampling bias, this should
be assessed and reported if material.
• Not applicable - manufactured sample
Sample security • The measures taken to ensure sample security. • The Chain of Custody was managed by Andromeda. Double
sealed samples were electronically tracked during transport
by commercial courier contractors between processing
facilities and analytical labs.
Audits or reviews • The results of any audits or reviews of sampling techniques and data. • No external audits have been undertaken
Andromeda Metals Limited | 9
Section 2 Reporting of Exploration Results
(Criteria listed in the preceding section also apply to this section.)
Criteria JORC Code explanation Commentary
Mineral
tenement and
land tenure
status
• Type, reference name/number, location and ownership including agreements or material
issues with third parties such as joint ventures, partnerships, overriding royalties, native
title interests, historical sites, wilderness or national park and environmental settings.
• The security of the tenure held at the time of reporting along with any known
impediments to obtaining a licence to operate in the area.
• The Great White Kaolin Project is located on ML 6532.
• The ML 6532 is held by Andromeda Industrial Minerals Pty Ltd,
a 100% owned subsidiary of Andromeda Metals Ltd.
• There are no known non-government royalties due.
• Andromeda owns the freehold land beneath ML 6532.
• The underlying land title being freehold has extinguished Native
Title.
• There are no known heritage sites within the Great White area
which preclude exploration or mineral development.
• All tenements are secure and compliant with requirements
issued by the Government of South Australia’s Department for
Energy and Mining (DEM) at the date of this report.
Exploration
done by other
parties
• Acknowledgment and appraisal of exploration by other parties. • Not applicable - manufactured product
Geology • Deposit type, geological setting and style of mineralisation. • Great White Kaolin deposit developed in situ by lateritic
weathering of the feldspar-rich Hiltaba Granite.
• The Great White kaolin deposit is a sub-horizontal zone of
kaolinised granite resting with a sharp contact on unweathered
granite. The kaolinised zone is overlain by loosely consolidated
Tertiary and Quaternary sediments.
• High quality kaolin-halloysite deposits occur extensively across
the Great White Project area
Drill hole
Information
• A summary of all information material to the understanding of the exploration results
including a tabulation of the following information for all Material drill holes:
o easting and northing of the drill hole collar
o elevation or RL (Reduced Level – elevation above sea level in metres) of the drill hole
collar
o dip and azimuth of the hole
o down hole length and interception depth
o hole length.
• If the exclusion of this information is justified on the basis that the information is not
Material and this exclusion does not detract from the understanding of the report, the
Competent Person should clearly explain why this is the case.
• Not applicable - manufactured product
Andromeda Metals Limited | 10
Criteria JORC Code explanation Commentary
Data
aggregation
methods
• In reporting Exploration Results, weighting averaging techniques, maximum and/or
minimum grade truncations (e.g. cutting of high grades) and cut-off grades are usually
Material and should be stated.
• Where aggregate intercepts incorporate short lengths of high grade results and longer
lengths of low grade results, the procedure used for such aggregation should be stated
and some typical examples of such aggregations should be shown in detail.
• The assumptions used for any reporting of metal equivalent values should be clearly
stated.
• Analyses have been conducted on a homogenised,
manufactured product.
• No weighting or averaging techniques have been applied, and
no maximum or minimum grade truncations or cut-off grades
have been used.
• No metal equivalent values have been reported.
Relationship
between
mineralisation
widths and
intercept
lengths
• These relationships are particularly important in the reporting of Exploration Results.
• If the geometry of the mineralisation with respect to the drill hole angle is known, its
nature should be reported.
• If it is not known and only the down hole lengths are reported, there should be a clear
statement to this effect (e.g. ‘down hole length, true width not known’).
• Not applicable - manufactured product
Diagrams • Appropriate maps and sections (with scales) and tabulations of intercepts should be
included for any significant discovery being reported These should include, but not be
limited to a plan view of drill hole collar locations and appropriate sectional views.
• Not applicable - manufactured product
Balanced
reporting
• Where comprehensive reporting of all Exploration Results is not practicable,
representative reporting of both low and high grades and/or widths should be practiced to
avoid misleading reporting of Exploration Results.
• Comprehensive results are reported.
Other
substantive
exploration
data
• Other exploration data, if meaningful and material, should be reported including (but not
limited to): geological observations; geophysical survey results; geochemical survey
results; bulk samples – size and method of treatment; metallurgical test results; bulk
density, groundwater, geotechnical and rock characteristics; potential deleterious or
contaminating substances.
• Not applicable - manufactured product
Further work • The nature and scale of planned further work (e.g. tests for lateral extensions or depth
extensions or large-scale step-out drilling).
• Diagrams clearly highlighting the areas of possible extensions, including the main
geological interpretations and future drilling areas, provided this information is not
commercially sensitive.
• Company is to commence a pilot plant operation to validate the
HPA process flowsheet on a semi-continuous, end-to-end basis.
Share your feedback